The Bureau of Land Management is planning to update the resource management plan for the Robinson Summit Substation Expansion and a new 525kV power line connection in Nevada. They’re asking the public to share ideas and concerns by June 20, 2025, to help shape the project’s environmental review. This update aims to support better energy infrastructure while protecting the land and community interests.

Analyzed Economic Effects

4 provisions identified: 3 benefits, 1 costs, 0 mixed.

BLM to consider utility corridor and 525 kV line

The BLM intends to amend the Ely District Resource Management Plan to consider a designated utility corridor on about 307 acres of public land in White Pine County, Nevada. The Project would include a 50-acre expansion of the Robinson Summit Substation, a new 1.3-mile single-circuit 525 kV transmission line in a new 200-foot right-of-way, and a new access road about 20 feet wide with 2-foot berms on each side.

Public scoping and comment deadline

You can submit comments on the scope, issues, and alternatives for this RMP amendment and environmental assessment by June 20, 2025, or within 15 days after the last public meeting, whichever is later. The BLM will hold at least one public scoping meeting in Ely, Nevada, with meeting dates announced at least 15 days in advance on the BLM's ePlanning site.

Tribal government-to-government consultation

The BLM will consult with Indian Tribal Nations on a government-to-government basis in accordance with Executive Order 13175 and BLM policy, and will give due consideration to tribal concerns including impacts on Indian trust assets and cultural resources. Federal, State, local agencies and Tribes may be invited to participate in the scoping process and could be asked to be cooperating agencies for the environmental analysis.

ACEC nominations excluded from this process

The BLM states that the scope of this land use planning process does not include addressing the evaluation or designation of Areas of Critical Environmental Concern (ACEC), and BLM is not considering ACEC nominations as part of this process. That means ACEC nominations will not be evaluated through this specific RMP amendment and EA.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Effective Date
5/20/2025
6/20/2025

Department and Agencies

Department
Independent Agency
Agency
Interior Department
Land Management Bureau
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register