Federal Paperwork Renewal Checks In With Certified Mine Blasters
Published Date: 5/21/2025
Notice
Summary
The Office of Surface Mining wants to renew its rules for certifying blasters—people who handle explosives safely in mining. This affects blasters and mining companies who must keep up with paperwork but won’t face new fees. You’ve got until June 20, 2025, to share your thoughts on these info collection rules.
Analyzed Economic Effects
2 provisions identified: 1 benefits, 1 costs, 0 mixed.
States must submit blaster program
If you are a State regulatory authority that wants to certify blasters, you must submit a blaster certification program to the Office of Surface Mining Reclamation and Enforcement (OSMRE) for approval. This is a one-time information collection with an estimated completion time of 320 hours, applies to 1 respondent and 1 response, and is required to obtain or retain a benefit under the rule.
No monetary fees for respondents
The Office of Surface Mining estimates the total annual non-hour burden cost for this information collection is $0, so respondents will not be charged any monetary fees as part of this ICR. The ICR is described as an extension of a currently approved collection (OMB Control Number 1029-0080).
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2025-21443, Rescission of Fee Rates
The Office of Surface Mining is officially wiping away old coal fee rates that covered 2012 to 2021 because they’re outdated. New fee rates have been in place since October 1, 2021, and this rule makes it official starting January 27, 2026—unless folks speak up by December 29, 2025. This change mainly affects coal producers and keeps the fee system fresh and fair for years to come.
2026-17821, Montana Regulatory Program
The Office of Surface Mining Reclamation and Enforcement (OSM) published a document in the Federal Register on August 21, 2026, not approving, with one exception, an amendment to the Montana regulatory program under the Surface Mining Control and Reclamation Act of 1977 (SMCRA). OSM made an error in the document by adding an entry to 30 CFR 926.12 at paragraph (c), a paragraph that already existed. This document corrects the final regulation.
2026-17333, Montana Regulatory Program
We, the Office of Surface Mining Reclamation and Enforcement (OSM), are denying an amendment to the Montana regulatory program under the Surface Mining Control and Reclamation Act of 1977 (SMCRA). Montana submitted this proposed amendment to OSM on its own initiative in response to a State law passed by the Montana Legislature (Senate Bill (SB) 392). The proposed amendment would have added a provision requiring equal application of court costs to the prevailing party in contested case proceedings by a court or administrative agency that issues a decision. The proposal would have also amended the Montana Code Annotated (MCA) to refer to the proposed equal application of court costs rule. Finally, SB 392 includes contingencies that apply to the proposed amendment but are not codified into the MCA: codification instructions, a severability clause, an effective date clause, and an applicability statement.
2026-17055, Montana Regulatory Program
The Office of Surface Mining Reclamation and Enforcement (OSM) is not approving, with one exception, an amendment to the Montana regulatory program under the Surface Mining Control and Reclamation Act of 1977 (SMCRA or the Act). The Montana legislature, specifically Montana House Bill 328, proposes to add a definition of affected drainage basin to the Montana Code Annotated (MCA). Additionally, House Bill 328 proposes changes to the Montana Code Annotated, pertaining to bond release application requirements.
2026-16318, North Dakota Regulatory Program
North Dakota is updating its rules for surface mining to make things clearer and more efficient. These changes include new timelines for permits, creating a new Environmental Quality department, and shifting some duties to a new Water Resources department. The updates take effect on September 10, 2026, and affect anyone involved in mining permits and environmental oversight in the state.
2026-16136, Ohio Regulatory Program
The Office of Surface Mining Reclamation and Enforcement (OSM), is approving, in part, two amendments to the Ohio regulatory program (the Ohio program) under the Surface Mining Control and Reclamation Act of 1977 (SMCRA or the Act). As proposed by Ohio, the amendment involves statutory and regulatory changes to its bonding program (i.e., revising Ohio's alternative bonding system and providing the option for an applicant to post full-cost performance securities) and also includes statutory and regulatory changes pertaining to other subjects, such as abandoned mine land program funding, permitting standards, valid existing rights, remining, blasting, and topsoil handling. Ohio submitted this amendment, in part, to satisfy a program condition related to bonding inadequacies. We are removing this program condition.
Previous / Next Documents
Previous: 2025-09025, Submission for OMB Review; Comment Request
The Department of Agriculture wants your thoughts on a survey they use to track cold storage of agricultural products. They’re asking for comments by June 20, 2025, to make sure the survey is useful and not too much work for folks who respond. This helps keep the survey clear, accurate, and easy to fill out without costing extra money or time.
Next: 2025-09027, Silicon Metal From Angola, Australia, the Lao People's Democratic Republic, and Norway: Initiation of Less-Than-Fair-Value Investigations
The U.S. Department of Commerce is starting investigations to see if silicon metal from Angola, Australia, Laos, and Norway is being sold unfairly cheap in the U.S. This affects companies importing silicon metal from these countries and could lead to new duties (extra taxes) to protect U.S. producers. The process kicked off in May 2025, so importers should watch for possible cost changes soon.