Peach Bottom Nuclear Plant License Extension Gets Environmental Review
Published Date: 5/30/2025
Notice
Summary
The Nuclear Regulatory Commission is asking the public to weigh in on extending the Peach Bottom Atomic Power Station’s license for 20 more years. This affects folks near Peach Bottom, Pennsylvania, and involves reviewing environmental impacts and possible alternatives. Comments are due by July 14, 2025, and hearing requests by July 29, 2025—keeping the community in the loop and the power flowing safely!
Analyzed Economic Effects
5 provisions identified: 2 benefits, 0 costs, 3 mixed.
Draft review of 20-year license renewal
The NRC issued a draft supplement that evaluates the environmental effects of a proposed Subsequent License Renewal (SLR) to extend Peach Bottom Atomic Power Station Units 2 and 3 for an additional 20 years. The NRC staff's preliminary recommendation is that the adverse environmental impacts are not so great that keeping the option of SLR would be unreasonable.
Exact proposed operating dates for extension
The draft supplement evaluates continued operation for Peach Bottom Unit 2 from August 8, 2033, through August 8, 2053, and for Unit 3 from July 2, 2034, through July 2, 2054. These are the SLR-term dates the NRC staff analyzed for environmental impacts.
Public comment and hearing deadlines
You can submit public comments on the draft supplement by July 14, 2025. If you want a hearing or to intervene (limited to contentions based on new information in the draft supplement), you must file a request or petition by July 29, 2025 (and petitions generally must be filed within 60 days of the notice).
Review uses updated environmental rules and guidance
The draft supplement incorporates new information including the NRC final rule revising 10 CFR part 51 published August 6, 2024, and Revision 2 of NUREG-1437 (dated August 2024) plus related Revision 2 guidance documents. The NRC staff used these updated rules and guidance as the technical basis for its environmental review.
How to get the draft documents
The draft supplement and related documents are available in the NRC ADAMS system (Accession No. ML25111A147) and at public access points, including the Harford County Public Library Whiteford Branch at 2407 Whiteford Road, Whiteford, MD 21160. For questions, the NRC lists a contact (Kevin Folk) with phone 301-415-6944 and an email address.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-19568, Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight
The Nuclear Regulatory Commission is updating rules for nuclear reactor licensing, shutting down old reactors, and keeping an eye on operations to make everything safer and clearer. These changes affect reactor operators and companies involved in decommissioning, with a public comment deadline on November 9, 2026. The updates aim to streamline processes and improve oversight without signaling big cost changes yet.
2026-14341, Modernizing Reactor Licensing, Safety Oversight, and Siting Practices
The Nuclear Regulatory Commission is updating the rules for how nuclear reactors get licensed, checked for safety, and where they can be built. These changes will make the process faster and clearer, helping new clean energy get on the grid sooner. If you want to share your thoughts, you have until August 31, 2026, to comment—this could also save money by cutting red tape!
2026-13687, Implementation of the National Environmental Policy Act
The Nuclear Regulatory Commission is updating how it follows the National Environmental Policy Act to make reviews faster, clearer, and less of a hassle. These changes affect anyone applying for nuclear licenses or permits, cutting down on paperwork and focusing only on important environmental impacts. You’ve got until August 21, 2026, to share your thoughts before the new rules take shape!
2026-12067, Fee Schedules; Fee Recovery for Fiscal Year 2026
The Nuclear Regulatory Commission is updating its fees for licenses, inspections, and special projects starting August 17, 2026. These changes make sure the NRC covers nearly all its costs while setting clear fee limits to keep prices predictable and fair. If you hold a license or apply for one, expect some fee adjustments that help the NRC run smoothly and efficiently.
2026-08550, Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles
The Nuclear Regulatory Commission is making it easier and faster to get licenses for small nuclear reactors, called microreactors, by creating simpler rules that match their lower risks. This change helps companies build more of these reactors quickly while keeping safety strong. If you’re involved in making or using these reactors, get ready to share your thoughts by June 15, 2026, and expect a smoother, less costly approval process soon.
2026-08015, Generic Environmental Impact Statement for Licensing of New Nuclear Reactors
The Nuclear Regulatory Commission just updated the rules for checking the environmental impact of new nuclear reactors. This makes it easier and faster to review many reactors by using a common set of environmental factors, while still looking closely at unique site details. The new rules kick in on May 26, 2026, helping companies save time and money when applying to build new reactors.
Previous / Next Documents
Previous: 2025-09449, Constellation Energy Generation, LLC; Dresden Nuclear Power Station, Units 2 and 3; Draft Supplemental Environmental Impact Statement
Constellation Energy wants to keep running its Dresden Nuclear Power Station, Units 2 and 3, near Joliet, Illinois, for even longer. The Nuclear Regulatory Commission is asking the public to share their thoughts on this plan by July 14, 2025. This decision affects local communities and energy users, with no big cost changes announced yet but important environmental impacts under review.
Next: 2025-09755, Determination of Regulatory Review Period for Purposes of Patent Extension; LOQTORZI
The FDA has officially set the review period for LOQTORZI, a new medicine, so its patent can be extended. This helps the company protect their invention longer, which could mean more time to make money from it. If anyone thinks the dates are wrong or wants to challenge the company’s effort during review, they must speak up by July 29 or November 26, 2025.