NRC Lists Routine Nuclear Plant License Changes for Review

Published Date: 7/8/2025

Notice

Summary

The Nuclear Regulatory Commission is sharing updates on changes to nuclear plant licenses that don’t pose big safety risks. These updates affect plant operators and the public, with a chance to comment or request hearings by early August and September 2025. No major cost or safety issues are expected, so plants can keep running smoothly while these changes happen.

Analyzed Economic Effects

5 provisions identified: 4 benefits, 1 costs, 0 mixed.

Amendments can take effect immediately

The NRC may issue a license amendment before the normal 60-day notice period if it determines the change involves no significant hazards consideration (NSHC). The Commission may also issue an amendment before the 30-day comment period ends if not acting would cause derating or shutdown of the facility.

Oyster Creek decommissioning plan added

Holtec's proposed amendment would incorporate the Oyster Creek Nuclear Generating Station License Termination Plan (LTP) into the license; the LTP outlines how the site will be decommissioned and how residual radioactivity will be addressed to meet criteria for unrestricted use, and upon approval the LTP would become a supplement to the station's Final Safety Analysis Report.

Public comment and hearing deadlines

You can submit public comments on the NRC's listed license amendments by August 7, 2025, and you can request a hearing or file a petition to intervene by September 8, 2025. The notice covers amendment actions proposed or issued from May 23, 2025, to June 18, 2025.

Ginna NaOH system completion time extended

R.E. Ginna Nuclear Power Plant's proposed amendment would extend the Required Action B completion time to restore the Sodium Hydroxide (NaOH) system from 72 hours to 14 days for Technical Specification 3.6.6.

Seabrook emergency action level change

NextEra's Seabrook Station proposed amendment would change the Emergency Action Levels for Initiating Condition HU4 in procedure ER 1.1, "Classification of Emergencies," due to the implementation of a new fire detection system inside the Seabrook Containment Building.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
7/8/2025

Department and Agencies

Department
Independent Agency
Agency
Nuclear Regulatory Commission
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register