2025-13226RuleWallet

NOAA Writes Rules for Accidental Marine-Mammal Encounters at Anchorage Port

Published Date: 7/15/2025

Rule

Summary

The Port of Alaska is upgrading its cargo terminals in Anchorage over five years, starting March 2026. This project might accidentally affect local marine mammals, so NOAA set rules to protect these animals while allowing construction to move forward safely. The rules include monitoring and reporting to keep the impact as low as possible without slowing down progress.

Analyzed Economic Effects

6 provisions identified: 2 benefits, 4 costs, 0 mixed.

Five-year incidental-take authorization

NOAA issued rules that allow the Port of Alaska to receive Letters of Authorization to incidentally take marine mammals during the Cargo Terminals Replacement project from March 1, 2026 through February 28, 2031. The rule covers specified construction activities at the Port of Alaska and sets the conditions under which incidental take is permitted.

Mandatory shutdowns and observer monitoring

The rule requires pre-clearance monitoring, use of approved Protected Species Observers (PSOs), and shutdowns when marine mammals (including Cook Inlet beluga whales) enter modeled Level B harassment zones. NMFS cites prior construction where shutdowns caused 228.5 hours of delay (about 23 ten-hour workdays).

Bubble curtains required for permanent piles

For all impact and vibratory driving of permanent 72-inch (1.83 m) piles in water deeper than 3 meters, the rule requires use of bubble curtains in all months. This is a construction mitigation requirement contractors must implement during those activities.

Bubble-curtain requirement relaxed for temporary piles (Aug–Oct)

NMFS removed the previously proposed requirement to use bubble curtains during vibratory installation and extraction of temporary piles in the months of August through October for this project. NMFS found practicability concerns and low effectiveness for that specific activity and period.

Seasonal and scale limits on in-water work

The CTR project in-water work is described as including installation of approximately 275 permanent piles and 450 temporary piles (and vibratory extraction of ~46 temporary piles) performed on about 337 nonconsecutive days between March and November in 2026 through 2030. That schedule and scope constrain when and how contractors must plan work.

Monitoring reports and recordkeeping required

The rule requires submittal of monitoring reports that summarize marine mammal species and behavior observations, construction shutdowns or delays, and construction work completed. These reports must be prepared and delivered as part of the Letter of Authorization requirements.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Rule Effective
7/15/2025
3/1/2026

Department and Agencies

Department
Independent Agency
Agency
Commerce Department
National Oceanic and Atmospheric Administration
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register