NRC Updates the Rulebook for One Spent-Fuel Cask System
Published Date: 7/29/2025
Rule
Summary
The Nuclear Regulatory Commission updated the rules for storing spent nuclear fuel using the TN Americas NUHOMS EOS Dry Storage System. This update adds new ways to load fuel, introduces a steel plate option, and improves safety checks with new software. These changes take effect on October 14, 2025, and mainly affect companies using this storage system, with no extra costs expected.
Analyzed Economic Effects
3 provisions identified: 3 benefits, 0 costs, 0 mixed.
Amendment No. 4: Use of modified casks allowed
If you are a power reactor licensee, you may load spent nuclear fuel into NUHOMS EOS casks meeting Amendment No. 4 to Certificate of Compliance No. 1042 starting October 14, 2025, unless significant adverse comments are received by August 28, 2025. Approval avoids the need for each licensee to request an exemption from 10 CFR 72.212 and 72.214, which the NRC says would otherwise increase administrative burden and costs to each licensee.
No backfit for existing users
Existing users of the NUHOMS EOS system are not required to adopt Amendment No. 4; Amendment No. 3 remains effective for existing users and adoption of Amendment No. 4 by current users is voluntary. Amendment No. 4 applies only to new casks fabricated and used under Amendment No. 4.
No significant impact on small entities
The NRC certifies that this direct final rule will not have a significant economic impact on a substantial number of small entities; it affects only nuclear power plant licensees and TN Americas LLC, which the NRC states are not small entities under the Regulatory Flexibility Act.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-19568, Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight
The Nuclear Regulatory Commission is updating rules for nuclear reactor licensing, shutting down old reactors, and keeping an eye on operations to make everything safer and clearer. These changes affect reactor operators and companies involved in decommissioning, with a public comment deadline on November 9, 2026. The updates aim to streamline processes and improve oversight without signaling big cost changes yet.
2026-14341, Modernizing Reactor Licensing, Safety Oversight, and Siting Practices
The Nuclear Regulatory Commission is updating the rules for how nuclear reactors get licensed, checked for safety, and where they can be built. These changes will make the process faster and clearer, helping new clean energy get on the grid sooner. If you want to share your thoughts, you have until August 31, 2026, to comment—this could also save money by cutting red tape!
2026-13687, Implementation of the National Environmental Policy Act
The Nuclear Regulatory Commission is updating how it follows the National Environmental Policy Act to make reviews faster, clearer, and less of a hassle. These changes affect anyone applying for nuclear licenses or permits, cutting down on paperwork and focusing only on important environmental impacts. You’ve got until August 21, 2026, to share your thoughts before the new rules take shape!
2026-12067, Fee Schedules; Fee Recovery for Fiscal Year 2026
The Nuclear Regulatory Commission is updating its fees for licenses, inspections, and special projects starting August 17, 2026. These changes make sure the NRC covers nearly all its costs while setting clear fee limits to keep prices predictable and fair. If you hold a license or apply for one, expect some fee adjustments that help the NRC run smoothly and efficiently.
2026-08550, Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles
The Nuclear Regulatory Commission is making it easier and faster to get licenses for small nuclear reactors, called microreactors, by creating simpler rules that match their lower risks. This change helps companies build more of these reactors quickly while keeping safety strong. If you’re involved in making or using these reactors, get ready to share your thoughts by June 15, 2026, and expect a smoother, less costly approval process soon.
2026-08015, Generic Environmental Impact Statement for Licensing of New Nuclear Reactors
The Nuclear Regulatory Commission just updated the rules for checking the environmental impact of new nuclear reactors. This makes it easier and faster to review many reactors by using a common set of environmental factors, while still looking closely at unique site details. The new rules kick in on May 26, 2026, helping companies save time and money when applying to build new reactors.
Previous / Next Documents
Previous: 2025-14291, Security Zone; Intracoastal Waterway, Palm Beach, FL
The Coast Guard is setting up a temporary security zone in Palm Beach's Intracoastal Waterway near Mar-A-Lago from July 29 to September 30, 2025. This zone activates only when the President, First Family, or Secret Service protectees are nearby to keep everyone safe from threats. Boaters and visitors should watch for enforcement during these times but won’t face new fees or costs.
Next: 2025-14295, Security Zones, Seattle's Seafair Fleet Week Moving Vessels, Puget Sound, WA
From July 29 to August 5, 2025, the Coast Guard will enforce security zones around Seattle’s Seafair Fleet Week moving vessels in Puget Sound to keep them safe from harm. Boats can’t enter within 500 yards of these ships without permission, but they can cruise slowly in the outer 400 yards. This means boaters need to plan ahead and follow new rules during the event to avoid fines or delays.