Palisades Nuclear Plant Gets Regulatory Green Light to Restart
Published Date: 7/29/2025
Notice
Summary
The Nuclear Regulatory Commission just gave Palisades Nuclear Plant the green light to restart power operations by lifting previous rules that stopped the reactor from running and loading fuel. This change affects Palisades Energy and Holtec, letting them operate the plant again starting July 24, 2025, without extra costs mentioned. It also cancels six old exemptions tied to the plant’s decommissioning status.
Analyzed Economic Effects
3 provisions identified: 2 benefits, 1 costs, 0 mixed.
One‑time exemption allows reactor restart
The NRC granted a one-time exemption to allow rescission of the docketed 10 CFR 50.82(a)(1) decommissioning certifications so the Palisades reactor may have fuel placed into the reactor vessel and resume power operations. The exemption was issued on July 24, 2025 and is effective August 25, 2025, but full operation depends on concurrent NRC approvals that were issued to restore the plant's power-operations licensing basis.
Operating authority transferred to Palisades Energy
The NRC approved the transfer of operating authority from Holtec Decommissioning International to Palisades Energy, LLC. The NRC issued the order approving and issuing a conforming amendment on July 24, 2025; Holtec Palisades, LLC remains the licensed owner.
Six decommissioning exemptions rescinded
The NRC rescinded six exemptions that had been granted based on Palisades being in decommissioning status. The six exemptions to be rescinded coincident with implementation of the exemption include: Certified Fuel Handlers Severe Weather Authority; Record Keeping; Use of Decommissioning Funds for Spent Fuel Management; Permanently Defueled Emergency Plan; Offsite Primary and Secondary Liability Insurance; and Onsite Property Damage Insurance.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-19568, Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight
The Nuclear Regulatory Commission is updating rules for nuclear reactor licensing, shutting down old reactors, and keeping an eye on operations to make everything safer and clearer. These changes affect reactor operators and companies involved in decommissioning, with a public comment deadline on November 9, 2026. The updates aim to streamline processes and improve oversight without signaling big cost changes yet.
2026-14341, Modernizing Reactor Licensing, Safety Oversight, and Siting Practices
The Nuclear Regulatory Commission is updating the rules for how nuclear reactors get licensed, checked for safety, and where they can be built. These changes will make the process faster and clearer, helping new clean energy get on the grid sooner. If you want to share your thoughts, you have until August 31, 2026, to comment—this could also save money by cutting red tape!
2026-13687, Implementation of the National Environmental Policy Act
The Nuclear Regulatory Commission is updating how it follows the National Environmental Policy Act to make reviews faster, clearer, and less of a hassle. These changes affect anyone applying for nuclear licenses or permits, cutting down on paperwork and focusing only on important environmental impacts. You’ve got until August 21, 2026, to share your thoughts before the new rules take shape!
2026-12067, Fee Schedules; Fee Recovery for Fiscal Year 2026
The Nuclear Regulatory Commission is updating its fees for licenses, inspections, and special projects starting August 17, 2026. These changes make sure the NRC covers nearly all its costs while setting clear fee limits to keep prices predictable and fair. If you hold a license or apply for one, expect some fee adjustments that help the NRC run smoothly and efficiently.
2026-08550, Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles
The Nuclear Regulatory Commission is making it easier and faster to get licenses for small nuclear reactors, called microreactors, by creating simpler rules that match their lower risks. This change helps companies build more of these reactors quickly while keeping safety strong. If you’re involved in making or using these reactors, get ready to share your thoughts by June 15, 2026, and expect a smoother, less costly approval process soon.
2026-08015, Generic Environmental Impact Statement for Licensing of New Nuclear Reactors
The Nuclear Regulatory Commission just updated the rules for checking the environmental impact of new nuclear reactors. This makes it easier and faster to review many reactors by using a common set of environmental factors, while still looking closely at unique site details. The new rules kick in on May 26, 2026, helping companies save time and money when applying to build new reactors.
Previous / Next Documents
Previous: 2025-14332, Center For Scientific Review; Notice of Closed Meetings
The Center for Scientific Review is holding several closed virtual meetings in September 2025 to review and evaluate important grant and contract proposals. These meetings protect private info and trade secrets while deciding which scientific projects get funding. Researchers and organizations applying for grants should note these dates as they impact funding decisions but don’t involve public attendance or new costs.
Next: 2025-14336, Agency Information Collection Activities
The Department of Justice fixed a mix-up with four important paperwork notices from July 10, 2025, which were published too early and didn’t allow public comments. Now, the correct notices are out as of July 23, 2025, and anyone affected—like dealers, agencies, and collectors—can comment until August 22, 2025. No new fees or deadlines changed, just a fresh chance to share your thoughts!