Sugar River Hydro Eyes Quiet Decommission, Environment Gets Say
Published Date: 8/28/2025
Notice
Summary
Sugar River Hydro II, LLC wants to shut down its hydroelectric project on the Sugar River in New Hampshire by removing electrical gear and closing the water intake, but leaving the dam in place. The government is preparing an environmental check to make sure this shutdown won’t harm the area, with a report expected by March 2026. Local groups and the public have already shared their thoughts, and more feedback will be welcomed soon.
Analyzed Economic Effects
4 provisions identified: 3 benefits, 0 costs, 1 mixed.
Hydro plant will stop producing power
Sugar River Hydro II filed to surrender its license and proposes to disconnect all generator leads, remove transformers and other electrical equipment, remove hydraulic and governor fluids and reservoirs, and close the penstock intake. The dam and gates would remain in place and an emergency backup system with a dedicated generator would be kept.
FERC will prepare an environmental assessment
The Federal Energy Regulatory Commission staff will prepare an environmental assessment (EA) under the National Environmental Policy Act and plans to issue the EA by March 2, 2026. Once issued, the EA will be available for a 30-day public comment period.
No new ground disturbance planned
The licensee does not anticipate any new ground disturbance while securing the powerhouse and closing the penstock intake. The penstock closure plan will be developed with the U.S. Fish and Wildlife Service and the New Hampshire Department of Environmental Services Dam Bureau.
Public help available to participate
The Commission's Office of Public Participation (OPP) offers assistance to members of the public—including landowners, community organizations, and Tribal members—to access information and help make filings such as comments or interventions. OPP contact information is provided (phone: (202) 502-6595 and email: OPP@ferc.gov).
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-20416, Commission Information Collection Activities (FERC-603); Comment Request; Extension
FERC is renewing its info collection form called FERC-603, which helps protect important energy infrastructure details. No changes are planned, but folks who submit this info should know the deadline to comment is November 5, 2026. This keeps the process smooth without adding extra costs or paperwork.
2026-20454, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got a bunch of new filings from energy companies like Rhode Island State Energy Center and Arizona Public Service. These filings include requests for approvals, status updates, and refund reports that could affect how electricity rates and projects move forward. If you’re involved in energy or power, keep an eye on deadlines for comments, mostly in October and November 2026, as some changes might impact costs or operations soon.
2026-20420, Combined Notice of Filings
The Federal Energy Regulatory Commission got several filings from natural gas pipeline companies about rate changes and refunds. These updates affect customers and companies using pipelines, with new rates starting as soon as October 1, 2026. If you want to comment, deadlines are mostly mid-October, so act fast to have your say on possible price changes.
2026-20421, PJM Interconnection, L.L.C.; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is checking if PJM Interconnection’s new rules for buying backup power are fair and legal. This affects energy companies and customers in the PJM region, with possible changes to how costs are shared. If refunds are needed, they start from October 6, 2026, and anyone interested has 21 days to speak up.
2026-20418, BIF III Holtwood LLC; Notice of Application for Non-Project Use of Project Land and Waters Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
BIF III Holtwood LLC wants to build docks on land and water near the Wallenpaupack Hydroelectric Project in Pennsylvania. The government is reviewing this request and asking the public to share their thoughts by October 30, 2026. This could change how the land and water are used but won’t affect electricity prices or timing.
2026-20453, Southern Star Central Gas Pipeline, Inc.; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Evergy McNew Power Plant Delivery Project
Southern Star Central Gas Pipeline wants to build new gas facilities to deliver power to the Evergy McNew Power Plant in Kansas. The government is asking the public to share their thoughts on how this might affect the environment before making a final decision. If you care about local air, water, or land, now’s the time to speak up by November 2, 2026!
Previous / Next Documents
Previous: 2025-16564, Valley Falls Associates; Albany Engineering Corporation; Notice of Transfer of Exemption
Valley Falls Associates has officially passed the torch for the James Thompson Hydroelectric Project to Albany Engineering Corporation. This change means Albany Engineering now runs the 2,500-kilowatt project on the Hoosic River in New York, with no extra approvals or fees needed. If you need to reach out, contact Albany Engineering starting now!
Next: 2025-16566, Polypropylene Corrugated Boxes From the People's Republic of China: Preliminary Affirmative Determination of Sales at Less Than Fair Value
The U.S. says China is selling polypropylene corrugated boxes in America for less than they should. This means importers might face extra duties soon, starting from July to December 2024. If you’re involved, now’s the time to speak up and share your thoughts!