EPA Grants Coal Plants Three More Years for Ash Pond Closures
Published Date: 11/28/2025
Proposed Rule
Summary
The EPA is giving coal power plants three more years to close big, unlined coal ash ponds, moving the deadline from 2028 to 2031. This helps some plants keep running longer to keep the lights on without rushing costly closures. If you own or run these sites, this extra time means more flexibility and a smoother transition.
Analyzed Economic Effects
4 provisions identified: 2 benefits, 1 costs, 1 mixed.
Three‑Year Extension for Large Coal‑Ash Ponds
The EPA proposes to move the deadline to complete closure of unlined coal combustion residual (CCR) surface impoundments larger than 40 acres from October 17, 2028 to October 17, 2031. This change applies only to owners/operators with extension demonstrations under 40 CFR 257.103(f)(2) and would allow placement of CCR and coal-fired generation at those sites to continue for up to three additional years.
Estimated Cost Savings and Preserved Capacity
EPA's Regulatory Impact Analysis estimates annualized cost savings from this proposed extension of about $7–12 million per year using a 3% discount rate, or about $17–27 million per year using a 7% discount rate. EPA also estimates the extension could preserve roughly 3,200 MW in MISO (about 10% of anticipated retirements), 1,056 MW in SPP (about 14%), and about 2,200 MW in PJM (about 13%) for up to three additional years.
Environmental Monitoring and Risk Mitigation Stay In Place
Facilities that operate under the extended deadline would remain subject to existing groundwater monitoring, assessment, and corrective action requirements (40 CFR 257.90–257.98) and their Part A risk mitigation plans. EPA will continue to review risk mitigation measures and may require additional measures as a condition of any extension.
No Extension for Small Impoundments
EPA is not proposing any extension for unlined CCR surface impoundments that are 40 acres or smaller; those owners/operators were required to cease coal-fired boiler operation and complete closure by October 17, 2023 and those impoundments have ceased receiving CCR and non‑CCR wastes.
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-09895 — Effluent Limitations Guidelines and Standards for the Steam Electric Power Generating Point Source Category-Unmanaged Combustion Residual Leachate
The EPA is updating rules for steam electric power plants to better control dirty water leaking from leftover coal waste. This change affects existing power plants and is expected to save up to $1 billion a year while protecting water quality. Comments on the proposal are open until June 17, 2026, so now’s the time to speak up!
2026-09524 — Begin Actual Construction in the New Source Review (NSR) Preconstruction Permitting Program
The EPA is updating rules about when companies can start building big projects that might affect air quality. Now, they can begin building parts that don’t release pollution before getting a full air permit, making things clearer and easier. This change mainly affects businesses planning major construction and could speed up projects without extra costs, but comments are due by June 29, 2026.
2026-09179 — Definition of Hazardous Waste Applicable to Corrective Action for Releases From Solid Waste Management Units; Withdrawal
The EPA has decided to cancel its plan to change the rules about what counts as hazardous waste for cleaning up pollution at certain waste sites. This means businesses and cleanup crews won’t have to deal with the confusing new rules that were proposed. The withdrawal takes effect immediately, so no extra costs or changes will happen right now.
2026-08750 — Extension of Postponement of Effectiveness for Certain Provisions of Trichloroethylene (TCE); Regulation Under the Toxic Substances Control Act (TSCA)
The EPA is hitting the pause button again on some rules about a chemical called TCE, which is used in workplaces. This means certain limited uses of TCE won’t have to follow new restrictions just yet, while courts review the rules. If you work with TCE, this delay gives you more time before changes kick in, starting May 18, 2026.
2026-07061 — Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Legacy/CCRMU Amendments
The EPA is updating rules on how electric utilities handle coal waste, making it easier to manage and reuse safely. These changes affect power plants and waste managers by allowing more flexible cleanup and reuse options, with a public comment deadline on June 12, 2026. The updates could save money and speed up cleanup while protecting the environment.
2026-06808 — Reconsideration of Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sources: Oil and Natural Gas Sector Climate Review
The EPA is making some technical fixes to rules for oil and natural gas companies about how they handle gas flaring and monitoring. These changes don’t change pollution limits but clarify how to report and test emissions. The new rules take effect June 8, 2026, helping companies stay on track without extra costs or delays.
Previous / Next Documents
Previous: 2025-21581 — Furnishing Identifying Number of Tax Return Preparer
The IRS is officially pulling back a plan from 2012 that would have set new rules for who can get a tax preparer ID number (PTIN). This affects tax return preparers, but because a court blocked the IRS from regulating them, no new rules or fees will happen. So, tax preparers can keep doing their thing without extra hoops or costs—for now!
Next: 2025-21620 — Build America: Eliminating Barriers to Wireless Deployments
The FCC wants to make it easier and faster to build wireless towers and other equipment by cutting through red tape that slows things down. This change will help companies and communities get better wireless service without unnecessary delays or extra costs. People and businesses should share their thoughts by December 31, 2025, to help shape these new rules.