EPA Dishes Out 2025 Pollution Credits to New Power Plants
Published Date: 3/2/2026
Notice
Summary
The EPA just shared the first numbers for how pollution allowances will be handed out to new power units in 2025 under the Cross-State Air Pollution Rule. Power plants that qualify can get these special allowances, but the EPA is open to hearing any objections until April 1, 2026, before finalizing the amounts. This helps keep pollution in check while giving new units a fair shot at trading pollution credits.
Analyzed Economic Effects
7 provisions identified: 3 benefits, 4 costs, 0 mixed.
Preliminary 2025 NUSA Allocations Posted
If you operate a qualifying new power unit, the EPA posted preliminary 2025 new unit set-aside (NUSA) allowance calculations online showing each unit's proposed 2025 allocation (generally equal to that unit's 2025 control period emissions reported under 40 CFR part 75). These are preliminary numbers for the 2025 control periods that the EPA may finalize after considering timely objections.
Pro-Rata Reductions If NUSA Oversubscribed
If the sum of eligible new-unit allocations exceeds the amount of allowances in a state's 2025 NUSA, the EPA will reduce each new unit's allocation on a pro-rata basis. That means your proposed allocation for 2025 could be cut back proportionally if the pool is oversubscribed.
Allocations May Be Corrected or Rescinded
The EPA says that an allocated allowance, or lack of one, does not determine whether a trading program applies to a unit, and allocations can be corrected if a unit with allocated allowances is not an 'affected unit' at the start of the 2025 control period. That means your allocation could be changed or removed if the unit's status changes.
NOX Ozone Season Group 3 Stayed for 2025
The EPA states it has no current plans to determine NUSA allocations for the 2025 control period under the CSAPR NOX Ozone Season Group 3 Trading Program because implementation of that program remains administratively stayed. Units that would fall under Group 3 should note this stay for 2025.
Early Emissions Excluded From Allocations
The EPA will not count emissions that occur before a unit's monitor certification deadline when calculating that unit's 2025 NUSA allocation. If your unit emitted before its monitor was certified, those early emissions will not increase your 2025 allocation.
Remaining Allowances Go To Existing Units
After the EPA allocates allowances to eligible new units for 2025, any allowances left in a state's NUSA are allocated to that state's existing units in proportion to those units' prior allocations from the non‑NUSA portion of the emissions budget. If you operate an existing unit, you may receive some of the leftover 2025 allowances based on past allocation shares.
Separate Indian Country NUSA Exists
For states that include Indian country, the CSAPR programs generally have a separate Indian country NUSA that reserves a portion of the emissions budget for units located in Indian country. Units located in Indian country are considered for allocations from that separate NUSA for the 2025 control periods.
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-09895 — Effluent Limitations Guidelines and Standards for the Steam Electric Power Generating Point Source Category-Unmanaged Combustion Residual Leachate
The EPA is updating rules for steam electric power plants to better control dirty water leaking from leftover coal waste. This change affects existing power plants and is expected to save up to $1 billion a year while protecting water quality. Comments on the proposal are open until June 17, 2026, so now’s the time to speak up!
2026-09524 — Begin Actual Construction in the New Source Review (NSR) Preconstruction Permitting Program
The EPA is updating rules about when companies can start building big projects that might affect air quality. Now, they can begin building parts that don’t release pollution before getting a full air permit, making things clearer and easier. This change mainly affects businesses planning major construction and could speed up projects without extra costs, but comments are due by June 29, 2026.
2026-09179 — Definition of Hazardous Waste Applicable to Corrective Action for Releases From Solid Waste Management Units; Withdrawal
The EPA has decided to cancel its plan to change the rules about what counts as hazardous waste for cleaning up pollution at certain waste sites. This means businesses and cleanup crews won’t have to deal with the confusing new rules that were proposed. The withdrawal takes effect immediately, so no extra costs or changes will happen right now.
2026-08750 — Extension of Postponement of Effectiveness for Certain Provisions of Trichloroethylene (TCE); Regulation Under the Toxic Substances Control Act (TSCA)
The EPA is hitting the pause button again on some rules about a chemical called TCE, which is used in workplaces. This means certain limited uses of TCE won’t have to follow new restrictions just yet, while courts review the rules. If you work with TCE, this delay gives you more time before changes kick in, starting May 18, 2026.
2026-07061 — Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Legacy/CCRMU Amendments
The EPA is updating rules on how electric utilities handle coal waste, making it easier to manage and reuse safely. These changes affect power plants and waste managers by allowing more flexible cleanup and reuse options, with a public comment deadline on June 12, 2026. The updates could save money and speed up cleanup while protecting the environment.
2026-06808 — Reconsideration of Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sources: Oil and Natural Gas Sector Climate Review
The EPA is making some technical fixes to rules for oil and natural gas companies about how they handle gas flaring and monitoring. These changes don’t change pollution limits but clarify how to report and test emissions. The new rules take effect June 8, 2026, helping companies stay on track without extra costs or delays.
Previous / Next Documents
Previous: 2026-04124 — Notice of Scope Ruling Applications Filed in Antidumping and Countervailing Duty Proceedings
The U.S. Department of Commerce is checking if certain products fall under special import taxes called antidumping and countervailing duties. Companies asked for these checks in January 2026, and the results could affect which products get taxed and when. This update helps businesses and the public stay in the loop about these important trade decisions starting March 2, 2026.
Next: 2026-04126 — Notice of Petition for Extension of Waiver of Compliance
The American Short Line and Regional Railroad Association asked for more time to skip some daily and periodic safety tests on Allegheny Valley Railroad’s equipment. If approved, they can double the time between certain tests, saving time and effort without cutting safety corners. People can share their thoughts on this by April 1, 2026.