The EPA said no to a request that challenged a pollution permit for the Passaic Valley Sewerage Commission’s wastewater plant in Newark, New Jersey. This means the plant can keep operating under its current permit, and anyone unhappy with this decision has until May 11, 2026, to take it to court. This keeps things steady for the plant and the community while following clean air rules.
Analyzed Economic Effects
2 provisions identified: 0 benefits, 0 costs, 2 mixed.
Wastewater Plant Keeps Current Permit
The EPA denied a petition and confirmed that Passaic Valley Sewerage Commission’s wastewater treatment facility in Newark, New Jersey may continue operating under Clean Air Act operating permit no. BOP210002 as of the EPA order dated February 3, 2026. This preserves the plant's current operating status and the existing regulatory conditions for the local community.
Deadline To Seek Judicial Review
Anyone seeking judicial review of the portions of the EPA order that denied issues in the petition must file a petition in the appropriate United States Court of Appeals no later than May 11, 2026. The order denying the petition was signed on February 3, 2026.
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-10086 — Extending the Compliance Deadline for the PFOA and PFOS Maximum Contaminant Levels
The EPA is giving water systems more time to meet safety rules for two harmful chemicals, PFOA and PFOS, by extending the deadline from April 2029 to April 2031 if they ask for it. This helps water providers get ready without rushing, keeping our drinking water safe. The EPA wants your thoughts and will hold a public hearing in July 2026 to hear from everyone.
2026-10085 — Rescission of Regulatory Determinations and Removal of Related Provisions for Four PFAS Substances (PFHxS, PFNA, HFPO-DA (GenX), and the Mixture of These Three PFAS Plus PFBS)
The EPA is proposing to undo its rules for four PFAS chemicals (PFHxS, PFNA, GenX, and a mix including PFBS) in drinking water because the original process wasn’t done right. This means public water systems won’t have to monitor or treat these chemicals for now. People and water providers should weigh in by July 20, 2026, and a virtual hearing happens July 7.
2026-09895 — Effluent Limitations Guidelines and Standards for the Steam Electric Power Generating Point Source Category-Unmanaged Combustion Residual Leachate
The EPA is updating rules for steam electric power plants to better control dirty water leaking from leftover coal waste. This change affects existing power plants and is expected to save up to $1 billion a year while protecting water quality. Comments on the proposal are open until June 17, 2026, so now’s the time to speak up!
2026-09524 — Begin Actual Construction in the New Source Review (NSR) Preconstruction Permitting Program
The EPA is updating rules about when companies can start building big projects that might affect air quality. Now, they can begin building parts that don’t release pollution before getting a full air permit, making things clearer and easier. This change mainly affects businesses planning major construction and could speed up projects without extra costs, but comments are due by June 29, 2026.
2026-09179 — Definition of Hazardous Waste Applicable to Corrective Action for Releases From Solid Waste Management Units; Withdrawal
The EPA has decided to cancel its plan to change the rules about what counts as hazardous waste for cleaning up pollution at certain waste sites. This means businesses and cleanup crews won’t have to deal with the confusing new rules that were proposed. The withdrawal takes effect immediately, so no extra costs or changes will happen right now.
2026-08750 — Extension of Postponement of Effectiveness for Certain Provisions of Trichloroethylene (TCE); Regulation Under the Toxic Substances Control Act (TSCA)
The EPA is hitting the pause button again on some rules about a chemical called TCE, which is used in workplaces. This means certain limited uses of TCE won’t have to follow new restrictions just yet, while courts review the rules. If you work with TCE, this delay gives you more time before changes kick in, starting May 18, 2026.
Previous / Next Documents
Previous: 2026-04852 — Proposed Consent Decree; Clean Air Act Citizen Suit
The EPA is settling a lawsuit about air pollution in California’s San Joaquin Valley. They missed a deadline to check if the air met clean air rules for tiny particles (PM2.5). This new agreement sets a clear deadline for the EPA to finish their review, helping protect the air we breathe without costing extra money right now.
Next: 2026-04854 — Petition for Exemption; Summary of Petition Received; Airborne Custom Spraying Inc.
Airborne Custom Spraying Inc. asked the FAA for a special exemption from some aviation rules to help their custom spraying flights run smoother. This affects pilots and companies in agricultural aviation, possibly speeding up operations without extra costs. The public can share their thoughts by April 1, 2026, so don’t miss your chance to weigh in!