FERC Logs New Natural Gas Rate Changes Starting April
Published Date: 3/16/2026
Notice
Summary
The Federal Energy Regulatory Commission got several new filings about natural gas pipeline rates and refunds. These filings mostly involve negotiated rate changes and a storm damage surcharge, all set to start on April 1, 2026. If you’re a company using these pipelines, keep an eye out because these changes could affect your costs soon, and comments are due by March 23, 2026.
Analyzed Economic Effects
2 provisions identified: 0 benefits, 1 costs, 1 mixed.
Negotiated Pipeline Rate Filings Effective 4/1/2026
Several natural gas pipelines filed negotiated-rate changes that are set to be effective on April 1, 2026. If your company buys pipeline capacity or gas transportation services, these filings could change the prices you pay for pipeline services.
High Island Storm Damage Surcharge 2026
High Island Offshore System filed a Storm Damage Surcharge that is set to be effective on April 1, 2026. If your company uses that pipeline, the surcharge would add extra charges to your pipeline bills to recover storm damage costs.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22877, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas companies about rate changes and reports. These updates could affect customers and businesses by changing pipeline rates or how penalties are handled, with some changes starting as soon as October 2026. If you want to speak up or get involved, you need to comment by specific deadlines in November or January.
2026-22803, Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Northern Illinois Hydropower, LLC asked for more time to start and finish building their Brandon Road Hydroelectric Project in Illinois. The project sits on federal land near Rockdale and needs approval from the Federal Energy Regulatory Commission (FERC). People have until December 4, 2026, to share their thoughts or objections, so this extension could affect the project’s timeline and future energy plans.
2026-22791, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from Texas Eastern Transmission and Enable Gas Transmission. These filings propose changes to contracts and rates starting November 1 or 5, 2026, which could affect customers and companies using these pipelines. If you want to speak up or get involved, you need to act by November 16, 2026.
2026-22721, Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to build new pipeline facilities in Pennsylvania to move more natural gas from the Marcellus Shale area. The government is preparing an environmental review to make sure the project is safe and will finish it by March 26, 2027. If all goes well, final approvals should happen by June 24, 2027, affecting local communities and energy customers with potential new energy options.
Previous / Next Documents
Previous: 2026-05055, Submission for OMB Review; Comment Request
The Department of Agriculture is asking for public feedback on a plan to collect info from states about how they spend money managing school meal programs. This update affects state agencies that handle programs like school lunches and breakfasts, aiming to make reporting clearer and easier. Comments are open until April 15, 2026, so states and others can share their thoughts before the plan moves forward.
Next: 2026-05057, White Pine Waterpower, LLC; Notice of Revised Schedule for White Pine Pumped Storage Project
White Pine Waterpower is taking extra time to finish an important water study for their pumped storage project, pushing back key review dates. This means the final decision on their license won’t come until October 2028, giving everyone more time to weigh in. The delay affects the company, regulators, and the community watching this clean energy project closely.