Summary
FERC is updating its rules about how electric companies plan for extreme weather to keep the power grid reliable. They want your thoughts on these changes by April 16, 2026. This affects electric companies and could mean better planning but no new costs for the public.
Analyzed Economic Effects
2 provisions identified: 1 benefits, 1 costs, 0 mixed.
Mandatory five-year extreme-temperature checks
If you are an electric planning coordinator or transmission planner, proposed Reliability Standard TPL-008-1 requires completing an "extreme temperature assessment" at least once every five calendar years. NERC's registry identifies 62 planning coordinators and 204 transmission planners that would be subject to this requirement.
Estimated industry paperwork burden and cost
The Commission estimates TPL-008-1 will generate 266 annual responses totaling 16,880 burden hours and $1,192,910 in annual labor costs. The estimate breaks down to 62 planning coordinator responses (88 hours each) and 204 transmission planner responses (56 hours each) at an hourly rate of $70.67.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-17101, Georgia Power Company; Notice of Application for Temporary Variance Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Georgia Power Company asked for a temporary change to rules at their Flint River Hydroelectric Project in Georgia. This could affect water quality rules and needs approval from state agencies. People have until September 17, 2026, to share their thoughts or get involved before any decisions are made.
2026-17103, Seefeld Corporation: Notice of Application for Surrender of Exemption Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Seefeld Corporation wants to give up its special exemption for the Smith Creek Hydroelectric Project in Washington. This change could affect local water quality rules and needs approval from the Washington Department of Ecology. People have until September 17, 2026, to share their thoughts or get involved before the decision moves forward.
2026-16925, Commission Information Collection Activities (FERC-725U); Comment Request; Extension
In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on the currently approved information collection FERC-725U (1902-0274), Mandatory Reliability Standards for the Bulk Power System; CIP Reliability Standards. There are no proposed changes to the reporting requirements. The comment period ended on July 27, 2026, with no comments received.
2026-16739, Venture Global CP2 LNG, LLC, Venture Global CP Express, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed CP2 LNG Expansion Project, and Notice of Public Scoping Sessions
2026-16616, Regulatory Agenda
We are publishing our regulatory agenda (the Agenda) in accordance with Public Law 96-354, "The Regulatory Flexibility Act," and Executive Order 12866, "Regulatory Planning and Review." FERC's complete Agenda, available on OMB's website at https://www.reginfo.gov, is a compilation of all rulemaking activities on which we have recently completed action or have proposed or are considering action. Our last Agenda was provided in May 2025 and in this current agenda, we have listed 42 rulemaking activities. We also note that the Agency has one inactive rulemaking that is not listed in this Agenda. This issuance of our Agenda contains ten (10) Pre-Rules, eleven (11) Notice of Proposed Rules, eight (8) Final Rules, and thirteen (13) Completed activities. Four (4) rulemakings are Section 3(f)(1) Significant; two (2) are Other Significant; one (1) is a routine rulemaking activity; two (2) are administrative, and thirty-two (32) are Substantive, Nonsignificant rulemaking activities.
2026-16637, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and rule updates. These changes could affect pipeline rates starting as soon as July 9, 2026, and some compliance updates kick in January 1, 2027. If you want to speak up or get involved, you need to comment by late August 2026.
Previous / Next Documents
Previous: 2026-05158, Combined Notice of Filings
The Federal Energy Regulatory Commission got a new filing from Iroquois Gas Transmission about their yearly fuel and loss costs. If you’re interested or affected, you have until March 24, 2026, to speak up or join the discussion. This could impact natural gas rates, so keep an eye on any changes that might affect your bills or services.
Next: 2026-05163, Self-Regulatory Organizations; BOX Exchange LLC; Notice of Filing and Immediate Effectiveness of a Proposed Rule Change To Adopt a New Methodology for Assessment and Collection of the Options Regulatory Fee (ORF)
BOX Exchange is changing how it charges the Options Regulatory Fee (ORF) by only charging fees for trades made directly on its platform. This new way won’t start until at least July 1, 2026, and only if other U.S. options exchanges agree to do the same by April 1. Traders using BOX and other options exchanges should watch for these updates, as it could affect their fees soon.