EPA Eases Rules for Burning Yard Waste in Disasters
Published Date: 3/20/2026
Proposed Rule
Summary
The EPA is updating rules for air curtain incinerators that burn only wood, yard waste, and clean lumber by combining existing rules and easing some permit requirements. They’re also allowing temporary use of certain incinerators during disasters without the usual strict rules. These changes mainly affect businesses using these incinerators and could save time and money, with comments open until May 4, 2026.
Analyzed Economic Effects
4 provisions identified: 3 benefits, 0 costs, 1 mixed.
Title V permit exemptions for ACIs
The EPA proposes to remove the Clean Air Act Title V permitting requirement for ACIs that only burn wood wastes, yard wastes, and clean lumber, provided the ACI is not located at a Title V major source or subject to Title V for other reasons. The agency says this change (to be reflected in new subpart Ca) is expected to produce cost savings and make it easier to use ACIs for disaster cleanup and wildfire mitigation.
New ACI testing deadlines and options
The proposal would require an initial performance test within 60 days of initial startup (shortening the prior up-to-180-day allowance) and would standardize annual performance testing to within 12 months of the previous test (SMWC previously allowed up to 13 months). It also would allow an owner/operator to delay the annual test until the next day the unit is operated if the ACI is not operating when the annual test would be due.
Temporary CISWI use for disaster cleanup
The EPA proposes to add provisions allowing temporary use of Commercial and Industrial Solid Waste Incineration (CISWI) units to burn debris from a qualifying disaster or emergency without complying with the usual CAA section 129 CISWI requirements, aligning CISWI with existing OSWI temporary-use provisions. The change is intended to speed disaster recovery operations by reducing regulatory barriers during qualified emergencies.
Simplified ACI opacity rules
The EPA proposes to move the opacity limits and monitoring, recordkeeping, and reporting for air curtain incinerators (ACI) that only burn wood wastes, yard wastes, and clean lumber into a single new subpart (40 CFR part 60 subpart Ca). The proposal would consolidate the 10 percent opacity limit during regular operation and the 35 percent opacity limit during startup and set a single averaging method consistent with 40 CFR 60.11(b) (6-minute averages).
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-10085 — Rescission of Regulatory Determinations and Removal of Related Provisions for Four PFAS Substances (PFHxS, PFNA, HFPO-DA (GenX), and the Mixture of These Three PFAS Plus PFBS)
The EPA is proposing to undo its rules for four PFAS chemicals (PFHxS, PFNA, GenX, and a mix including PFBS) in drinking water because the original process wasn’t done right. This means public water systems won’t have to monitor or treat these chemicals for now. People and water providers should weigh in by July 20, 2026, and a virtual hearing happens July 7.
2026-10086 — Extending the Compliance Deadline for the PFOA and PFOS Maximum Contaminant Levels
The EPA is giving water systems more time to meet safety rules for two harmful chemicals, PFOA and PFOS, by extending the deadline from April 2029 to April 2031 if they ask for it. This helps water providers get ready without rushing, keeping our drinking water safe. The EPA wants your thoughts and will hold a public hearing in July 2026 to hear from everyone.
2026-09895 — Effluent Limitations Guidelines and Standards for the Steam Electric Power Generating Point Source Category-Unmanaged Combustion Residual Leachate
The EPA is updating rules for steam electric power plants to better control dirty water leaking from leftover coal waste. This change affects existing power plants and is expected to save up to $1 billion a year while protecting water quality. Comments on the proposal are open until June 17, 2026, so now’s the time to speak up!
2026-09524 — Begin Actual Construction in the New Source Review (NSR) Preconstruction Permitting Program
The EPA is updating rules about when companies can start building big projects that might affect air quality. Now, they can begin building parts that don’t release pollution before getting a full air permit, making things clearer and easier. This change mainly affects businesses planning major construction and could speed up projects without extra costs, but comments are due by June 29, 2026.
2026-09179 — Definition of Hazardous Waste Applicable to Corrective Action for Releases From Solid Waste Management Units; Withdrawal
The EPA has decided to cancel its plan to change the rules about what counts as hazardous waste for cleaning up pollution at certain waste sites. This means businesses and cleanup crews won’t have to deal with the confusing new rules that were proposed. The withdrawal takes effect immediately, so no extra costs or changes will happen right now.
2026-08750 — Extension of Postponement of Effectiveness for Certain Provisions of Trichloroethylene (TCE); Regulation Under the Toxic Substances Control Act (TSCA)
The EPA is hitting the pause button again on some rules about a chemical called TCE, which is used in workplaces. This means certain limited uses of TCE won’t have to follow new restrictions just yet, while courts review the rules. If you work with TCE, this delay gives you more time before changes kick in, starting May 18, 2026.
Previous / Next Documents
Previous: C1-2026-04304 — National Emission Standards for Marine Tank Vessel Loading Operations: Technology Review
The EPA is updating rules for loading marine tank vessels to cut down harmful emissions. This affects companies that load oil and chemicals onto ships, aiming to use better technology and cleaner methods. Changes include corrected deadlines in March 2026, with no big cost surprises but a push for smarter, greener loading soon.
Next: 2026-05494 — Proposed Amendment of Class C Airspace at Raleigh-Durham International Airport, NC; Public Meeting
The FAA wants to change the airspace rules around Raleigh-Durham International Airport to improve local flight safety and operations. If you fly or live near KRDU, this affects you! Join a free virtual meeting on May 6, 2026, to learn more and share your thoughts before June 5, 2026. No costs or fees are involved, just your voice and ideas!