Summary
Texas Eastern Transmission wants to retire 13.45 miles of an old, unused gas pipeline under the Gulf near Louisiana to save money on upkeep. This $39.6 million project affects local energy infrastructure and is open for public feedback before the deadline. If you care about energy or the environment, now’s the time to speak up or get involved!
Analyzed Economic Effects
3 provisions identified: 2 benefits, 1 costs, 0 mixed.
Offshore Pipeline Abandonment Filed
On March 31, 2026, Texas Eastern filed to decommission and abandon in place 13.45 miles of its idle 24-inch Line 40-B-4-D segment 9888 in federal waters in the Gulf near Louisiana. The company estimates the project cost at $39,600,000 and says the work will eliminate the need for future maintenance and repair capital expenditures on that segment.
Free Public Comment and Intervention Rights
You can file a protest, motion to intervene, or comment in this FERC docket for free; submissions must be filed by 5:00 p.m. Eastern Time on June 9, 2026. Only intervenors have the right to request rehearing of Commission orders and to challenge those orders in federal court.
Protest Deadline Triggers Automatic Authorization
If no protest is filed by the 5:00 p.m. Eastern Time June 9, 2026 deadline, or if a filed protest is withdrawn within 30 days after the filing deadline, the proposed activity will be deemed authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the filing deadline, the Commission will consider the request.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22877, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas companies about rate changes and reports. These updates could affect customers and businesses by changing pipeline rates or how penalties are handled, with some changes starting as soon as October 2026. If you want to speak up or get involved, you need to comment by specific deadlines in November or January.
2026-22803, Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Northern Illinois Hydropower, LLC asked for more time to start and finish building their Brandon Road Hydroelectric Project in Illinois. The project sits on federal land near Rockdale and needs approval from the Federal Energy Regulatory Commission (FERC). People have until December 4, 2026, to share their thoughts or objections, so this extension could affect the project’s timeline and future energy plans.
2026-22791, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from Texas Eastern Transmission and Enable Gas Transmission. These filings propose changes to contracts and rates starting November 1 or 5, 2026, which could affect customers and companies using these pipelines. If you want to speak up or get involved, you need to act by November 16, 2026.
2026-22721, Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to build new pipeline facilities in Pennsylvania to move more natural gas from the Marcellus Shale area. The government is preparing an environmental review to make sure the project is safe and will finish it by March 26, 2027. If all goes well, final approvals should happen by June 24, 2027, affecting local communities and energy customers with potential new energy options.
Previous / Next Documents
Previous: 2026-07324, Agency Information Collection Activities; Proposed Collection; Comment Request; ICR Type Extension: Form 144-Notice of Proposed Sale of Securities Pursuant to Rule 144 Under the Securities Act of 1933
The SEC is asking to keep using Form 144, which helps people report big sales of certain stocks to keep things fair and clear. About 11,500 folks file this form nearly three times a year, spending about an hour each time. No big changes or costs are coming, but the SEC wants your thoughts on how to make the process better and easier.
Next: 2026-07326, Enable Mississippi River Transmission, LLC; Notice of Availability of the Environmental Assessment for the Proposed Ameren-Emrt Big Hollow Project
Enable Mississippi River Transmission, LLC wants to build a new natural gas pipeline in Illinois and Missouri to supply Ameren’s Big Hollow Energy Center with cleaner energy. The project aims to replace an old power plant and deliver lots of gas daily, helping the region’s energy future. People have until May 11, 2026, to share their thoughts before the project moves forward.