2026-08707Notice

Rio Grande LNG Seeks Extension to 2031 for Texas Terminal

Published Date: 5/5/2026

Notice

Summary

Rio Grande LNG and its partners asked for more time—until November 22, 2031—to finish building their big natural gas terminal in Texas. Construction is moving, but delays mean the last part won’t be ready until 2031, pushing back the original 2026 deadline. This extension helps keep the project on track without rushing, affecting local energy plans and investments.

No Economic Impacts Identified for this Document

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
5/5/2026

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission