Nuclear Startup Gets Three Extra Years to Finish Test Reactor
Published Date: 5/18/2026
Notice
Summary
Kairos Power got the green light to take more time building their Hermes test reactor in Oak Ridge, Tennessee. The deadline to finish construction moved from the end of 2026 to April 30, 2029, giving them extra breathing room. This change helps Kairos keep their project on track without rushing, but it means the wait for this cool new reactor just got a bit longer.
No Economic Impacts Identified for this Document
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-19568, Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight
The Nuclear Regulatory Commission is updating rules for nuclear reactor licensing, shutting down old reactors, and keeping an eye on operations to make everything safer and clearer. These changes affect reactor operators and companies involved in decommissioning, with a public comment deadline on November 9, 2026. The updates aim to streamline processes and improve oversight without signaling big cost changes yet.
2026-14341, Modernizing Reactor Licensing, Safety Oversight, and Siting Practices
The Nuclear Regulatory Commission is updating the rules for how nuclear reactors get licensed, checked for safety, and where they can be built. These changes will make the process faster and clearer, helping new clean energy get on the grid sooner. If you want to share your thoughts, you have until August 31, 2026, to comment—this could also save money by cutting red tape!
2026-13687, Implementation of the National Environmental Policy Act
The Nuclear Regulatory Commission is updating how it follows the National Environmental Policy Act to make reviews faster, clearer, and less of a hassle. These changes affect anyone applying for nuclear licenses or permits, cutting down on paperwork and focusing only on important environmental impacts. You’ve got until August 21, 2026, to share your thoughts before the new rules take shape!
2026-12067, Fee Schedules; Fee Recovery for Fiscal Year 2026
The Nuclear Regulatory Commission is updating its fees for licenses, inspections, and special projects starting August 17, 2026. These changes make sure the NRC covers nearly all its costs while setting clear fee limits to keep prices predictable and fair. If you hold a license or apply for one, expect some fee adjustments that help the NRC run smoothly and efficiently.
2026-08550, Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles
The Nuclear Regulatory Commission is making it easier and faster to get licenses for small nuclear reactors, called microreactors, by creating simpler rules that match their lower risks. This change helps companies build more of these reactors quickly while keeping safety strong. If you’re involved in making or using these reactors, get ready to share your thoughts by June 15, 2026, and expect a smoother, less costly approval process soon.
2026-08015, Generic Environmental Impact Statement for Licensing of New Nuclear Reactors
The Nuclear Regulatory Commission just updated the rules for checking the environmental impact of new nuclear reactors. This makes it easier and faster to review many reactors by using a common set of environmental factors, while still looking closely at unique site details. The new rules kick in on May 26, 2026, helping companies save time and money when applying to build new reactors.
Previous / Next Documents
Previous: 2026-09879, Fee for Fingerprints Collected by CBP
Starting June 18, 2026, anyone applying for unescorted access to CBP security areas at airports will have to pay a new fee for fingerprint collection. This fee covers the FBI’s fingerprint check and CBP’s processing costs. If you’re submitting a paper application or need new fingerprints because TSA’s are missing or unreadable, this change affects you—and yes, it means a little extra cash out of pocket.
Next: 2026-09881, In the Matter of Arizona Public Service Company; El Paso Electric Company; Palo Verde Nuclear Generating Station, Units 1, 2, and 3 and Independent Spent Fuel Storage Installation; Indirect Transfer of Control of Licenses
The Nuclear Regulatory Commission approved a change in who controls part of the Palo Verde Nuclear Plant’s licenses. A private individual bought a one-third share from another, but Arizona Public Service still owns nearly 30% and keeps operating control. This change took effect May 5, 2026, and lasts for one year, with no immediate cost impact for the public.