2026-17101NoticeWallet

Georgia Power Seeks Hydro Rule Timeout: Comments Wanted

Published Date: 8/21/2026

Notice

Summary

Georgia Power Company asked for a temporary change to rules at their Flint River Hydroelectric Project in Georgia. This could affect water quality rules and needs approval from state agencies. People have until September 17, 2026, to share their thoughts or get involved before any decisions are made.

Analyzed Economic Effects

1 provisions identified: 1 benefits, 0 costs, 0 mixed.

Lake Worth drawdown for shoreline work

Georgia Power plans to lower Lake Worth about 5.0 feet from the normal lower target elevation of 181.3 feet to 176.3 feet starting September 21, 2026. The drawdown will proceed at one half-foot per day, reach the target on September 30, 2026, and remain for four weeks until refilling begins November 1, 2026 to allow installation and maintenance of shoreline structures.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Effective Date
8/21/2026
9/21/2026

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML