Summary

No summary available.

Analyzed Economic Effects

2 provisions identified: 0 benefits, 2 costs, 0 mixed.

Easement Negotiations and Eminent Domain Risk

If you are a landowner in Sweetwater County, Wyoming, the pipeline company may contact you to negotiate an easement to build and operate facilities. You do not have to agree, but if the Commission approves the project the Natural Gas Act gives the company the right to seek condemnation in court; compensation would be decided by a judge under state law.

Land Disturbance and Permanent Land Use Loss

Construction for the proposed project would disturb about 114 acres of land and Overthrust would maintain about 44 acres for permanent operation in Sweetwater County, Wyoming; the remaining acreage would be restored. If your property is within the project area, you could lose temporary use during construction and permanent use for the portion kept for operation.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Effective Date
9/4/2026
10/1/2026

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register