Gas Pipelines Flood FERC with Rate Tweak Filings Again
Published Date: 10/1/2026
Notice
Summary
The Federal Energy Regulatory Commission got a bunch of filings from natural gas pipeline companies about changing their rates and agreements. These changes mostly take effect starting November 1, 2026, and could affect how much customers pay or how companies handle fuel and losses. If you’re involved with these pipelines, keep an eye on comment deadlines in early to mid-October to have your say!
Analyzed Economic Effects
3 provisions identified: 1 benefits, 0 costs, 2 mixed.
Multiple pipeline rate changes pending
The Federal Energy Regulatory Commission received many Natural Gas Pipeline rate and agreement filings with most showing an effective date of November 1, 2026. Some filings list other effective dates (for example, Columbia Gas of Ohio’s SOC revision effective 2026-08-27 and certain compliance filings effective 2027-01-01). These filings ask to change rates or negotiated agreements and therefore could affect how much pipeline customers pay.
Fuel, line-loss, and operational reports filed
Several filings are for 2026 fuel and line-loss reports and operational purchase-and-sale reports (for example, Tuscarora Gas Transmission Company’s 2026 Fuel & Line Loss Report and Alliance Pipeline L.P.’s 2026 Fuel Filing listed with effective date 2026-11-01). The filings concern how pipelines account for fuel, line loss, and operational purchases and sales, which can affect how pipeline companies allocate costs.
Early–mid October comment deadlines
If you want to intervene, protest, or comment on any listed docket, you must file by the specified comment dates in October 2026 (examples include 5:00 p.m. ET on 2026-10-06, 2026-10-07, 2026-10-09, 2026-10-13, and 2026-10-16). Intervention is required to become a party to the proceeding; protests must be filed by the listed protest dates.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22877, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas companies about rate changes and reports. These updates could affect customers and businesses by changing pipeline rates or how penalties are handled, with some changes starting as soon as October 2026. If you want to speak up or get involved, you need to comment by specific deadlines in November or January.
2026-22803, Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Northern Illinois Hydropower, LLC asked for more time to start and finish building their Brandon Road Hydroelectric Project in Illinois. The project sits on federal land near Rockdale and needs approval from the Federal Energy Regulatory Commission (FERC). People have until December 4, 2026, to share their thoughts or objections, so this extension could affect the project’s timeline and future energy plans.
2026-22791, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from Texas Eastern Transmission and Enable Gas Transmission. These filings propose changes to contracts and rates starting November 1 or 5, 2026, which could affect customers and companies using these pipelines. If you want to speak up or get involved, you need to act by November 16, 2026.
2026-22721, Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to build new pipeline facilities in Pennsylvania to move more natural gas from the Marcellus Shale area. The government is preparing an environmental review to make sure the project is safe and will finish it by March 26, 2027. If all goes well, final approvals should happen by June 24, 2027, affecting local communities and energy customers with potential new energy options.
Previous / Next Documents
Previous: 2026-20105, The City of Columbus, Ohio; Notice of Application for Surrender of Exemption Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
The City of Columbus, Ohio, wants to give up its special exemption for the O'Shaughnessy Dam Hydroelectric Facility on the Scioto River. This change could affect local energy rules and requires approval from environmental agencies, with public comments due by October 28, 2026. If you care about local energy or the environment, now’s the time to speak up!
Next: 2026-20107, Ohio Power and Light, LLC; Notice of Availability of Environmental Assessment
Ohio Power and Light wants to build a new 28.5-megawatt hydroelectric project at the Robert C. Byrd Locks and Dam on the Ohio River in West Virginia. The government checked the environmental impact and says it won’t harm the area if done right. People have until October 28, 2026, to share their thoughts before the project moves forward.