Oops! Hydro Boss Misses Deadline, Loses Idaho Power Play
Published Date: 10/8/2026
Notice
Summary
Willis D. Deveny, the current license holder for the Shingle Creek Hydroelectric Project in Idaho, missed the deadline to say if they plan to renew their license before it expires in 2031. Because of this, they can’t apply for a new license later, and others interested in the project are now invited to step up and file their own applications. This is a big chance for new players to get involved before the clock runs out!
Analyzed Economic Effects
2 provisions identified: 1 benefits, 1 costs, 0 mixed.
Current licensee lost right to reapply
The current licensee, Willis D. Deveny, failed to file the required notice of intent (NOI) by the August 31, 2026 deadline. Because of that missed NOI, the existing licensee may not file an application for a subsequent license for the Shingle Creek Project (license expires August 31, 2031), either alone or with others.
Open chance for new applicants with deadlines
Because the current licensee missed the NOI deadline, other parties may file a notice of intent (NOI) and a pre-application document (PAD) to seek the Shingle Creek license. Interested applicants must file those documents within 120 days of October 2, 2026 (the date of this notice), and any subsequent license application must be filed by August 31, 2029 (24 months before the license expires). The project is a 224-kilowatt facility located on Shingle Creek in Idaho County, Idaho.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-23133, Combined Notice of Filings #2
The Federal Energy Regulatory Commission received several filings affecting solar energy companies, power pools, and utility providers. These filings include status updates, tariff changes, and agreement amendments set to take effect between September 2026 and January 2027. If you’re involved with these companies or rely on their services, keep an eye on upcoming deadlines for comments and possible rate or service changes.
2026-23132, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates and refunds from several companies, including National Fuel Gas and BBT Alabama. These filings propose changes to rates starting November 1 or 2, 2026, and invite public comments by late November or early January 2027. If you’re involved or interested, now’s the time to speak up before deadlines hit, as these changes could affect gas prices and services.
2026-22946, International Falls Power Company; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed International Falls Hydroelectric Project
International Falls Power Company wants to renew its license to run a hydroelectric project on the Rainy River in Minnesota. The government is asking the public to share their thoughts on how this project might affect the environment before deciding. If you care about clean energy or local nature, now’s the time to speak up—your input could shape the future of this power plant!
2026-22949, GB Energy Park, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
GB Energy Park, LLC is asking for more time to start and finish building their Gordon Butte Pumped Storage Project in Montana. This affects local communities and energy users waiting for this new hydroelectric power source. The public can share their thoughts or objections by December 7, 2026, so don’t miss your chance to weigh in!
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
Previous / Next Documents
Previous: 2026-20576, Agency Information Collection Activities: Information Collection Renewal; Comment Request; Community Reinvestment Act Qualifying Activity Confirmation Request Form
The Office of the Comptroller of the Currency (OCC) is renewing its form that banks use to confirm activities qualifying under the Community Reinvestment Act. This renewal aims to keep paperwork manageable and invites public comments by December 7, 2026. Banks and community groups involved in CRA activities should take note, but no new fees or major changes are expected.
Next: 2026-20578, Brown Bear II Hydro, Inc.; Notice of Intent To Prepare an Environmental Assessment
Brown Bear II Hydro wants to renew its license for the Worumbo Hydroelectric Project in Maine, which produces 19.4 megawatts of power. The government will prepare an Environmental Assessment to check if the project affects the environment, and the public can comment on it for 30 days. This process helps decide if the project can keep running without major changes or costs.