Shutting Down Ohio's Dusty Gas Well, No Drama

Published Date: 10/15/2026

Notice

Summary

Columbia Gas Transmission wants to safely shut down an old gas well and pipeline in Ohio to reduce risks without affecting service. The project costs about $900,000 and won’t impact customers or storage operations. If you want to speak up or get involved, you have until December 8, 2026, to file your comments or protests.

Analyzed Economic Effects

2 provisions identified: 2 benefits, 0 costs, 0 mixed.

Shutting an Old Gas Well to Reduce Risk

Columbia Gas Transmission wants to plug and abandon one injection/withdrawal well and its connecting pipeline in the Holmes Storage Field in Holmes County, Ohio (Holmes Well 10412 Abandonment Project). The company estimates the project will cost $900,000, will reduce integrity risks from aging storage infrastructure, and will have no adverse effect on certificated storage operations or customer service.

Public Filing Deadline to Intervene or Protest

You may file a protest, a motion to intervene, or comments about this project at no cost, but you must do so by 5:00 p.m. Eastern Time on December 8, 2026. Filings may be made using FERC's eFiling (eRegister) or by mailing a paper copy to the Secretary at the addresses in the notice.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
10/15/2026

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission