Ohio River Hydropower Developer Requests More Time for Construction

Published Date: 11/9/2026

Notice

Summary

FFP Missouri 5, LLC asked for more time to start and finish building a hydroelectric project at the Emsworth Locks and Dam on the Ohio River. This affects local energy plans and federal land use, with a chance for the public to share their thoughts by early December 2026. No new costs were announced, but the delay could shift project timelines.

Analyzed Economic Effects

1 provisions identified: 0 benefits, 0 costs, 1 mixed.

Two-Year Extension Requested for Hydropower Build

FFP Missouri 5, LLC asked the Federal Energy Regulatory Commission for a two-year extension to start and finish building the Emsworth Locks and Dam Hydroelectric Project. The current deadlines to commence and complete construction are May 5, 2027 and May 5, 2030; the company asks to extend those to May 5, 2029 and May 5, 2032. Public comments on the request are due by December 4, 2026 at 5:00 p.m. Eastern Time.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
11/9/2026

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register