Summary

From February 28 to September 30, 2027, the Coast Guard is setting up temporary safety zones in parts of Massachusetts Bay near Boston to keep everyone safe during underwater demolition work. Boats and people can’t enter these zones unless they get special permission from the Coast Guard. This helps protect workers and the public without costing anyone extra money.

Analyzed Economic Effects

6 provisions identified: 5 benefits, 1 costs, 0 mixed.

Seabed Restoration and Charting After Removal

The decommissioning will cut 16 suction caisson anchors 3 feet below the mudline, cap and backfill them to restore a flat, trawlable seafloor, recover approximately 141 concrete mattresses to shore, and require Neptune to submit certified high‑resolution 'as‑left' hydrographic surveys to NOAA to update navigational charts.

500‑meter No‑Entry Safety Zone

From 11:59 p.m. February 28, 2027 through 8 a.m. September 30, 2027, all navigable waters of Massachusetts Bay within a 500‑meter radius of the primary construction vessel (approx. posn 42°28'52.1'' N, 070°46'16.9'' W) are safety zones. No vessel or person may enter these moving safety zones unless specifically authorized by the Captain of the Port (COTP) or a designated representative.

Safety Zones Move With Work Vessels

The 500‑meter safety zones are moving zones that will be centered on the active decommissioning construction vessel(s) as work shifts among sites; typically one zone will be enforced except for a three‑week period when two zones may be active. The Coast Guard will announce exact locations and vessel names in advance via the Local Notice to Mariners and broadcast notices.

How to Request Entry Permission

If you need to enter a safety zone, you must obtain permission from the Captain of the Port (COTP) or a designated representative. Contact is available on VHF‑FM channel 16 or by calling the Coast Guard Sector Boston Command Center at (857) 416‑3015.

Protected‑Species and Timing Limits on Work

Operations must follow protected species mitigation including certified Protected Species Observers (PSOs) onboard, mandatory 10‑knot vessel speed caps within designated North Atlantic right whale areas, and a seasonal work window: no offshore decommissioning activities will occur between October 1 and January 31.

Coast Guard Finds No Significant Small‑Entity Impact

Under the Regulatory Flexibility Act, the Coast Guard certified that this temporary rule 'would not have a significant economic impact on a substantial number of small entities' because the zone affects a small area, vessel traffic can transit around it, and notices allow adjustment of transit plans.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Rule Effective
11/13/2026
2/28/2027

Department and Agencies

Department
Independent Agency
Agency
Homeland Security Department
Coast Guard
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register