Hydropower Operator Seeks Temporary Detour for New York River Project
Published Date: 11/13/2026
Notice
Summary
Eagle Creek Hydro Power and its partners asked for a temporary change to their Swinging Bridge Hydroelectric Project on the Mongaup River in New York. This change could affect local water use and power generation, and the public has until December 9, 2026, to share their thoughts or get involved. No big money changes are mentioned, but the decision could impact how the project runs for a short time.
Analyzed Economic Effects
2 provisions identified: 0 benefits, 2 costs, 0 mixed.
Temporary minimum flow reduced to 50 cfs
If you live near or use water from the Mongaup River at the Swinging Bridge project, the licensee proposes to lower the project's minimum flow from its current 100 cubic feet per second (cfs) or inflow (but no less than 60 cfs) to 50 cfs (or inflow if less). This temporary change would last up to 60 calendar days, approximately December 19, 2026, to January 30, 2027, and the 60-day period may be shifted with Commission authorization.
Unit 3 offline; reliance on siphon for flows
The licensee says reassembling generating unit no. 2 requires closing a headgate shared with generating unit no. 3, which will make unit no. 3 unavailable. During that period (up to 60 days between about December 19, 2026 and January 30, 2027), the project would rely solely on a reservoir-fed siphon system designed to provide between 50 and 60 cfs.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-23133, Combined Notice of Filings #2
The Federal Energy Regulatory Commission received several filings affecting solar energy companies, power pools, and utility providers. These filings include status updates, tariff changes, and agreement amendments set to take effect between September 2026 and January 2027. If you’re involved with these companies or rely on their services, keep an eye on upcoming deadlines for comments and possible rate or service changes.
2026-23132, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates and refunds from several companies, including National Fuel Gas and BBT Alabama. These filings propose changes to rates starting November 1 or 2, 2026, and invite public comments by late November or early January 2027. If you’re involved or interested, now’s the time to speak up before deadlines hit, as these changes could affect gas prices and services.
2026-22946, International Falls Power Company; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed International Falls Hydroelectric Project
International Falls Power Company wants to renew its license to run a hydroelectric project on the Rainy River in Minnesota. The government is asking the public to share their thoughts on how this project might affect the environment before deciding. If you care about clean energy or local nature, now’s the time to speak up—your input could shape the future of this power plant!
2026-22949, GB Energy Park, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
GB Energy Park, LLC is asking for more time to start and finish building their Gordon Butte Pumped Storage Project in Montana. This affects local communities and energy users waiting for this new hydroelectric power source. The public can share their thoughts or objections by December 7, 2026, so don’t miss your chance to weigh in!
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
Previous / Next Documents
Previous: 2026-23167, Final Flood Hazard Determinations
Starting March 16, 2027, new flood risk maps will take effect for certain communities, changing flood zones and water levels. Homeowners, renters, and local governments in these areas should check the updated maps to understand their flood risks and insurance needs. These changes could affect flood insurance costs and building rules, so it’s smart to stay informed and prepared!
Next: 2026-23170, Equitrans, L.P.; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Equitrans, L.P. wants to build a new 4.91-mile pipeline in West Virginia to deliver more natural gas—up to 108,000 dekatherms daily—to a new power plant by Wolf Summit Energy. The project will cost about $46.7 million and aims to boost energy delivery on their mainline system. If you want to speak up or get involved, you have until January 8, 2027, to file your comments or protests.