One Compressor Station Pushes a Gas Project Deadline to 2029

Published Date: 11/13/2026

Notice

Summary

Iroquois Gas Transmission System needs more time to finish building a gas project in New York and Connecticut because one part still needs state approval. They’ve already gotten federal OKs and started work on most stations, but the Brookfield Compressor Station is holding things up. The new deadline to complete everything is March 25, 2029, giving them extra time without extra costs announced yet.

No Economic Impacts Identified for this Document

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
11/13/2026

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register