Dry River Means Temporary Flow Cut at New England Dam
Published Date: 11/16/2026
Notice
Summary
Great River Hydro, LLC wants to temporarily reduce water flow at the Fifteen Mile Falls Hydroelectric Project because of low river levels caused by less rain. This change affects communities near the Connecticut River in New Hampshire and Vermont and will last until the end of 2026. The government is preparing an environmental check and will ask for public feedback before making a final decision.
Analyzed Economic Effects
2 provisions identified: 1 benefits, 0 costs, 1 mixed.
Temporary cut to river minimum flows
You live near the Connecticut River in Grafton County, New Hampshire, or Caledonia County, Vermont, the licensee plans to reduce required minimum flows to 600 cubic feet per second (cfs). The change would lower the seasonal minimums of 818 cfs (June 1–September 30) and 1,145 cfs (October 1–March 31) down to 600 cfs, starting when the Moore reservoir drops two feet below its historic minimum operating level and forecasts are below required minimums, and ending on December 31, 2026.
Environmental assessment and public comment window
You can participate in the review: Commission staff plans to prepare an environmental assessment (EA) and issue it by December 30, 2026, and the EA will be issued for a 30-day public comment period. All comments filed on the EA will be reviewed and considered in the Commission's final decision on the proceeding.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-23133, Combined Notice of Filings #2
The Federal Energy Regulatory Commission received several filings affecting solar energy companies, power pools, and utility providers. These filings include status updates, tariff changes, and agreement amendments set to take effect between September 2026 and January 2027. If you’re involved with these companies or rely on their services, keep an eye on upcoming deadlines for comments and possible rate or service changes.
2026-23132, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates and refunds from several companies, including National Fuel Gas and BBT Alabama. These filings propose changes to rates starting November 1 or 2, 2026, and invite public comments by late November or early January 2027. If you’re involved or interested, now’s the time to speak up before deadlines hit, as these changes could affect gas prices and services.
2026-22946, International Falls Power Company; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed International Falls Hydroelectric Project
International Falls Power Company wants to renew its license to run a hydroelectric project on the Rainy River in Minnesota. The government is asking the public to share their thoughts on how this project might affect the environment before deciding. If you care about clean energy or local nature, now’s the time to speak up—your input could shape the future of this power plant!
2026-22949, GB Energy Park, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
GB Energy Park, LLC is asking for more time to start and finish building their Gordon Butte Pumped Storage Project in Montana. This affects local communities and energy users waiting for this new hydroelectric power source. The public can share their thoughts or objections by December 7, 2026, so don’t miss your chance to weigh in!
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
Previous / Next Documents
Previous: 2026-23227, Notice on Outer Continental Shelf Oil and Gas Lease Sales
Starting November 1, 2026, through April 30, 2027, certain big oil and gas companies can’t team up to bid on Outer Continental Shelf leases. This keeps the playing field fair and competitive for all bidders. If you’re a company producing over 1.6 million barrels daily, watch out—you might get disqualified from bidding!
Next: 2026-23232, Delfin LNG LLC; Notice of Request for Extension of Time
Delfin LNG LLC is asking for more time—until September 28, 2030—to finish building important onshore facilities in Louisiana that help transport natural gas to their deepwater port. They’ve already gotten several extensions because their big $5 billion floating LNG vessel won’t arrive until 2030. This delay affects construction deadlines but keeps the project moving forward without extra costs right now.