Dam Keeps Its Reservoir After the Hydropower Project Closes
Published Date: 11/24/2026
Notice
Summary
The City of Columbus plans to shut down and safely seal the O'Shaughnessy Dam hydroelectric project on the Scioto River, keeping the dam and reservoir for water supply. The Federal Energy Regulatory Commission will prepare an environmental assessment by June 25, 2027, to review the impact. This affects local residents and the environment, with no federal land involved and no public objections so far.
Analyzed Economic Effects
2 provisions identified: 2 benefits, 0 costs, 0 mixed.
Dam kept to supply Columbus water
The City of Columbus filed on July 6, 2026 to surrender the hydroelectric exemption for the O'Shaughnessy Dam project (Project No. 2943) on the Scioto River in Delaware County, Ohio. The city proposes to decommission the hydroelectric components but would keep the dam and reservoir in place to provide the City's water supply.
Public environmental review and comment window
The Federal Energy Regulatory Commission staff will prepare an environmental assessment (EA) and plans to issue the EA by June 25, 2027. The EA will be released for a 30-day public comment period during which members of the public can file comments that the Commission will review before deciding.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-23833, FERC Form 580 Interrogatories on Fuel and Energy Purchase Practices; Notice of Request for Partial Waiver
DTE Electric Company asked FERC to skip part of the 2026 fuel and energy purchase questions on Form 580. This affects companies that report fuel and energy buying info to FERC and could change how they share data. If you want to speak up or join the discussion, you need to act before the deadline!
2026-23834, Spire MoGas Pipeline LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Spire MoGas Pipeline is boosting its pipeline capacity by 25,000 dekatherms per day in eastern Missouri and southwestern Illinois—no new construction or costs needed! This means more natural gas can flow smoothly and reliably for customers in those areas. If you want to speak up or learn more, you’ve got until the set deadline to jump in and make your voice heard.
2026-23884, Denial of Rehearing Requests by Operation of Law Under the Commission's Rules of Practice and Procedure
The Federal Energy Regulatory Commission is updating its rules about rehearing requests. Now, if the Commission doesn’t respond within 30 days, the request is only denied for cases under the Federal Power Act and Natural Gas Act. This change kicks in on December 24, 2026, and mainly affects companies and individuals involved in energy regulation, helping clarify when they can move to court.
2026-23883, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates and rules from Louisville Gas & Electric, Kentucky Utilities, and El Paso Natural Gas. These filings ask for temporary rule changes and a rate update starting January 1, 2027. If you want to join the conversation or protest, you need to act by late November or early December 2026.
2026-23890, Bonneville Power Administration; Notice of Filing
Bonneville Power Administration wants to change its power rates starting February 1, 2027. If you’re a customer or interested party, you can speak up by December 17, 2026. This could affect how much you pay for electricity, so don’t miss your chance to weigh in!
2026-23891, Enable Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Enable Gas Transmission wants to lower the pressure limits on five pipeline delivery lines in Arkansas to keep things safe and run smoother. This change helps them avoid costly fixes like pipe replacements or pressure tests, with no new construction needed. If you’re interested, you have until a set deadline to speak up or protest this plan.
Previous / Next Documents
Previous: 2026-23888, Forestport Hydro, LLC; Notice of Availability of Environmental Assessment
Forestport Hydro, LLC wants to keep running its hydroelectric project on the Black River in New York. The government checked the environmental impact and says it’s safe to continue with some protective rules. If you want to share your thoughts, you’ve got until December 21, 2026, to speak up—no big costs or delays expected!
Next: 2026-23890, Bonneville Power Administration; Notice of Filing
Bonneville Power Administration wants to change its power rates starting February 1, 2027. If you’re a customer or interested party, you can speak up by December 17, 2026. This could affect how much you pay for electricity, so don’t miss your chance to weigh in!