Nuclear Waste Report Deadline Moves, Pending Research and a 2033 Backstop
Published Date: 11/27/2026
Notice
Summary
Northern States Power Company wants to change a deadline for safety reports about storing spent nuclear fuel at Prairie Island in Minnesota. They’re asking to push back the first report due date from 2028 to either six months after a key research report comes out or 2033, whichever comes first. This affects local communities and regulators, with a chance to speak up by January 26, 2027.
Analyzed Economic Effects
2 provisions identified: 1 benefits, 1 costs, 0 mixed.
Safety-report deadline pushed back
Northern States Power Company asked to change the first required safety evaluation deadline for high-burnup spent fuel at the Prairie Island ISFSI from April 4, 2028, to either within six months after the EPRI/DOE High Burnup Dry Storage Cask Research and Development Project (HDRP) initial storage period report is published or April 4, 2033, whichever is earlier.
Deadline to request a hearing
Anyone whose interest may be affected can request a hearing or petition to intervene in the NRC process, but petitions must be filed by January 26, 2027 (60 days after this notice's publication).
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-19568, Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight
The Nuclear Regulatory Commission is updating rules for nuclear reactor licensing, shutting down old reactors, and keeping an eye on operations to make everything safer and clearer. These changes affect reactor operators and companies involved in decommissioning, with a public comment deadline on November 9, 2026. The updates aim to streamline processes and improve oversight without signaling big cost changes yet.
2026-14341, Modernizing Reactor Licensing, Safety Oversight, and Siting Practices
The Nuclear Regulatory Commission is updating the rules for how nuclear reactors get licensed, checked for safety, and where they can be built. These changes will make the process faster and clearer, helping new clean energy get on the grid sooner. If you want to share your thoughts, you have until August 31, 2026, to comment—this could also save money by cutting red tape!
2026-13687, Implementation of the National Environmental Policy Act
The Nuclear Regulatory Commission is updating how it follows the National Environmental Policy Act to make reviews faster, clearer, and less of a hassle. These changes affect anyone applying for nuclear licenses or permits, cutting down on paperwork and focusing only on important environmental impacts. You’ve got until August 21, 2026, to share your thoughts before the new rules take shape!
2026-12067, Fee Schedules; Fee Recovery for Fiscal Year 2026
The Nuclear Regulatory Commission is updating its fees for licenses, inspections, and special projects starting August 17, 2026. These changes make sure the NRC covers nearly all its costs while setting clear fee limits to keep prices predictable and fair. If you hold a license or apply for one, expect some fee adjustments that help the NRC run smoothly and efficiently.
2026-08550, Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles
The Nuclear Regulatory Commission is making it easier and faster to get licenses for small nuclear reactors, called microreactors, by creating simpler rules that match their lower risks. This change helps companies build more of these reactors quickly while keeping safety strong. If you’re involved in making or using these reactors, get ready to share your thoughts by June 15, 2026, and expect a smoother, less costly approval process soon.
2026-08015, Generic Environmental Impact Statement for Licensing of New Nuclear Reactors
The Nuclear Regulatory Commission just updated the rules for checking the environmental impact of new nuclear reactors. This makes it easier and faster to review many reactors by using a common set of environmental factors, while still looking closely at unique site details. The new rules kick in on May 26, 2026, helping companies save time and money when applying to build new reactors.
Previous / Next Documents
Previous: 2026-24074, 60-Day Notice of Proposed Information Collection: Housing Opportunities for Persons With AIDS (HOPWA) Program
HUD wants to update the forms used by groups helping people with AIDS find housing through the HOPWA program. They’re asking for public feedback by January 26, 2027, to improve reporting and closeout rules, making sure the info collected is useful and not too much. This affects all current and future HOPWA grant recipients and aims to keep the program running smoothly without extra costs.
Next: 2026-24076, Extending Deadlines for Submissions by Importers of Automobiles Qualifying for Preferential Tariff Treatment Under the USMCA To Determine U.S. Content
Importers of cars that qualify for special USMCA tariff deals now have more time to send in proof showing how much U.S. content their vehicles have. This deadline extension means importers can avoid extra tariffs if they submit their documents starting November 27, 2026. It’s a win for businesses wanting to save money and keep things running smoothly.