North Dakota Pipeline Expansion Gets Its Environmental Assessment Notice
Published Date: 11/27/2026
Notice
Summary
WBI Energy wants to build a new 17-mile natural gas pipeline and upgrade a connection in North Dakota to help power a new electric station. This project will boost gas delivery by 190,000 dekatherms daily, supporting cleaner energy. People have until December 23, 2026, to share their thoughts before the project moves forward.
Analyzed Economic Effects
4 provisions identified: 2 benefits, 0 costs, 2 mixed.
New 17.2-mile natural gas pipeline
WBI Energy requests authorization to build and operate about 17.2 miles of 24-inch-diameter interstate natural gas transmission pipeline in Williams County, North Dakota, modify an existing interconnect in McKenzie County, and construct a meter station and related facilities. The notice identifies these specific facilities as the project components FERC reviewed in the Environmental Assessment.
Adds 190,000 dekatherms/day firm capacity
The project would provide 190,000 dekatherms per day of incremental firm transportation service to Basin Electric Power Cooperative's new Bison Generation Station. The Environmental Assessment evaluates this proposed delivery of incremental firm service as the project's purpose.
Public comment deadline and access rules
You may submit comments on the Environmental Assessment to FERC by 5:00 p.m. Eastern Time on December 23, 2026, using eComment, eFiling, or by mail referencing docket number CP26-158-000. The notice also states that filing comments does not give you intervenor status, and that the timeframe for timely intervention has expired but motions to intervene out-of-time may be filed under the Commission's Rule 214.
Environmental Assessment available electronically
The Environmental Assessment is available only in electronic format and can be viewed or downloaded from FERC's website or the eLibrary using docket number CP26-158. The notice provides contact information for FERC Online Support and TTY for assistance.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-24081, Combined Notice of Filings
The Federal Energy Regulatory Commission got several filings from natural gas pipeline companies about rates and refunds starting December 1, 2026, and January 1, 2027. These filings could affect how much customers pay or get refunded for natural gas services. If you want to speak up or comment, you’ve got until early December to do it!
2026-24005, Commission Information Collection Activities (FERC-153); Comment Request; Extension
FERC is extending its info collection process (FERC-153) for three more years without any changes. This means folks who interact with FERC can keep sharing their feedback on services to help improve them. Comments on this extension are due by January 25, 2027, and there’s no new cost or extra paperwork involved.
2026-23833, FERC Form 580 Interrogatories on Fuel and Energy Purchase Practices; Notice of Request for Partial Waiver
DTE Electric Company asked FERC to skip part of the 2026 fuel and energy purchase questions on Form 580. This affects companies that report fuel and energy buying info to FERC and could change how they share data. If you want to speak up or join the discussion, you need to act before the deadline!
2026-23834, Spire MoGas Pipeline LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Spire MoGas Pipeline is boosting its pipeline capacity by 25,000 dekatherms per day in eastern Missouri and southwestern Illinois—no new construction or costs needed! This means more natural gas can flow smoothly and reliably for customers in those areas. If you want to speak up or learn more, you’ve got until the set deadline to jump in and make your voice heard.
2026-23890, Bonneville Power Administration; Notice of Filing
Bonneville Power Administration wants to change its power rates starting February 1, 2027. If you’re a customer or interested party, you can speak up by December 17, 2026. This could affect how much you pay for electricity, so don’t miss your chance to weigh in!
2026-23892, Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Columbia Gas Transmission wants to upgrade a big pipeline in Ohio to make safety checks easier and better. They plan to spend about $26.3 million to add special equipment that helps inspect the pipeline inside. If you care about this project, you have until a set deadline to speak up or get involved.
Previous / Next Documents
Previous: 2026-24102, Leopold, Diane G.; Notice of Filing
Diane G. Leopold asked for permission to hold multiple important energy jobs at once. If you want to speak up or get involved, you need to act by the deadline set by the Federal Energy Regulatory Commission. This process doesn’t cost money but affects people working in energy regulation and those who want to weigh in on the decision.
Next: 2026-24107, American SI Exports Program; On-Demand Consortia for Specific Foreign Opportunities
Starting November 30, 2026, U.S. companies working with Super Intelligence (SI) tech can join new On-Demand Consortia to team up and export their innovations abroad. This fresh pathway makes it easier and faster to apply anytime, helping American SI businesses grow globally. The Department of Commerce will keep things flexible by allowing updates and reopening other program options later.