NRC Proposes Tighter Security for Nuclear Power Plants
Published Date: 1/31/2025
Proposed Rule
Summary
The Nuclear Regulatory Commission is updating rules to improve how law enforcement responds to security at nuclear power plants. These changes affect power reactor operators and law enforcement teams, aiming to boost safety and quick action during threats. The new rules are proposed now, with details on timing and costs to be shared soon, so everyone can get ready and stay safe.
No Economic Impacts Identified for this Document
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-19568, Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight
The Nuclear Regulatory Commission is updating rules for nuclear reactor licensing, shutting down old reactors, and keeping an eye on operations to make everything safer and clearer. These changes affect reactor operators and companies involved in decommissioning, with a public comment deadline on November 9, 2026. The updates aim to streamline processes and improve oversight without signaling big cost changes yet.
2026-14341, Modernizing Reactor Licensing, Safety Oversight, and Siting Practices
The Nuclear Regulatory Commission is updating the rules for how nuclear reactors get licensed, checked for safety, and where they can be built. These changes will make the process faster and clearer, helping new clean energy get on the grid sooner. If you want to share your thoughts, you have until August 31, 2026, to comment—this could also save money by cutting red tape!
2026-13687, Implementation of the National Environmental Policy Act
The Nuclear Regulatory Commission is updating how it follows the National Environmental Policy Act to make reviews faster, clearer, and less of a hassle. These changes affect anyone applying for nuclear licenses or permits, cutting down on paperwork and focusing only on important environmental impacts. You’ve got until August 21, 2026, to share your thoughts before the new rules take shape!
2026-12067, Fee Schedules; Fee Recovery for Fiscal Year 2026
The Nuclear Regulatory Commission is updating its fees for licenses, inspections, and special projects starting August 17, 2026. These changes make sure the NRC covers nearly all its costs while setting clear fee limits to keep prices predictable and fair. If you hold a license or apply for one, expect some fee adjustments that help the NRC run smoothly and efficiently.
2026-08550, Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles
The Nuclear Regulatory Commission is making it easier and faster to get licenses for small nuclear reactors, called microreactors, by creating simpler rules that match their lower risks. This change helps companies build more of these reactors quickly while keeping safety strong. If you’re involved in making or using these reactors, get ready to share your thoughts by June 15, 2026, and expect a smoother, less costly approval process soon.
2026-08015, Generic Environmental Impact Statement for Licensing of New Nuclear Reactors
The Nuclear Regulatory Commission just updated the rules for checking the environmental impact of new nuclear reactors. This makes it easier and faster to review many reactors by using a common set of environmental factors, while still looking closely at unique site details. The new rules kick in on May 26, 2026, helping companies save time and money when applying to build new reactors.
Previous / Next Documents
Previous: 2025-02022, Petition for Rulemaking of Central Office of Reform and Efficiency (Rules of Practice)
The Federal Trade Commission got a request to make rules clearer about how fast they must reply to petitions for rule changes. This affects anyone who files petitions, making the process more transparent and timely. You’ve got until March 3, 2025, to share your thoughts—no cost to comment, just your voice!
Next: 2025-02036, Draft Regulatory Guide: Acceptability of ASME Code, Section III, Division 5, “High Temperature Reactors”
The Nuclear Regulatory Commission (NRC) is giving everyone more time to share their thoughts on new rules about high-temperature nuclear reactors. These rules use a special safety code called ASME Section III, Division 5, and affect companies building or running these reactors. If you want to comment, you have until February 26, 2025, so don’t miss your chance to speak up!