153 sections in this chapter.
18 AAC 75-360 Cleanup operation requirements
8.3K chars
A responsible person shall ensure that site cleanup is conducted or supervised by a qualified environmental professional. A responsible person shall submit each of the following elements for approval before work on that element begins, and for additional approval if a modificatio…
18 AAC 75-365 Offsite or portable treatment facilities
6.7K chars
(a) A person who owns or operates an offsite or portable treatment facility shall (1) obtain approval of an operations plan before that person accepts or treats contaminated soil; the department will approve the plan if the department determines that the operations proposed in th…
18 AAC 75-370 75.370
5.0K chars
(a) Unless the department approves the activity in question as protective of human health, safety, and welfare, and of the environment, a responsible person may not blend contaminated soil with uncontaminated soil and shall (1) segregate contaminated soil based on (A) the intende…
18 AAC 75-375 Institutional controls
3.6K chars
(a) The department will, after consultation with each landowner of the site, determine that the use of an institutional control is necessary, on a site-specific basis, if the department determines that controls are required to ensure (1) compliance with an applicable cleanup leve…
18 AAC 75-380 Final reporting requirements and site closure
6.6K chars
(a) A responsible person shall submit a written final cleanup report to the department for each site undergoing cleanup under the site cleanup rules. The report must be prepared by a qualified environmental professional. (b) The written report required by (a) of this section must…
18 AAC 75-385 Appeals
0.7K chars
A person aggrieved by a final department decision under 18 AAC 75.380 or a final department decision revoking an approval issued under the site cleanup rules may request informal review under 18 AAC 15.185 or may reguest an adjudicatory hearing under 18 AAC 15.195 - 18 AAC 15.340…
18 AAC 75-390 Waiver or modification
3.0K chars
(a) Except as provided in (b) of this section, and if the department determines that a waiver or modification will be protective of human health, safety, and welfare, and of the environment, the department will waive or modify the site cleanup rules based on a review of the quant…
18 AAC 75-395 Interference with cleanup prohibited
0.6K chars
A person may not interfere with, hinder, or obstruct the containment or cleanup of a hazardous substance conducted under this chapter. This prohibition does not apply to the United States Coast Guard or EPA. Notes 18 AAC 75.395 Eff. 1/22/99, Register 149 Authority:AS 46.03.020 AS…
18 AAC 75-396 75.396
0.7K chars
Subject to AS 29.35.020, AS 46.04.110, and AS 46.09.060, the requirements of 18 AAC 75.300 - 18 AAC 75.390 do not preempt local control that is as stringent as, or more stringent than, those requirements, and that is consistent with a regional master plan prepared under AS 46.04.…
18 AAC 75-400 Applicability
6.3K chars
(a) A person who is subject to AS 46.04.030 or AS 46.04.055(j) must file an application for approval of an oil discharge prevention and contingency plan as required under 18 AAC 75.400 - 18 AAC 75.420 and meet the applicable requirements of 18 AAC 75.430 - 18 AAC 75.495. Notwiths…
18 AAC 75-402 Delayed implementation dates
3.3K chars
(a) If a person applies for a new plan under 18 AAC 75.410, an amendment determined to be a major amendment under 18 AAC 75.415(a), or a plan renewal under 18 AAC 75.420, and that person submits an application before August 4, 2023, the department will review the application unde…
18 AAC 75-405 Pre-application notification and consultation for oil discharge prevention and contingency plans; new plans and plan renewals
1.8K chars
(a) At least 60 days before the scheduled submission date for an application package for approval of a new oil discharge prevention and contingency plan under 18 AAC 75.410 or for renewal of approval under 18 AAC 75.420, the applicant must notify the department in writing of its …
18 AAC 75-408 General procedures to apply for oil discharge and contingency plans
5.3K chars
(a) An application package for approval of an oil discharge prevention and contingency plan must contain (1) an application form supplied by the department containing (A) the applicant's legal name, address, and telephone number; (B) the name, location, and type of facility or op…
18 AAC 75-410 Procedures to apply for oil discharge prevention and contingency plans; new plans
1.1K chars
(a) An application package for approval of a new oil discharge prevention and contingency plan must be submitted in accordance with 18 AAC 75.408. An application package must be submitted at least 180 days before the proposed start of operation. (b) Repealed 4/16/2016. (c) The de…
18 AAC 75-412 Transitional provisions for review of plans approved before May 14, 1992 (Repealed)
0.4K chars
Notes 18 AAC 75.412 Eff. 5/14/92, Register 122; repealed 11/27/2002, Register 164 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features wil…
18 AAC 75-413 Transitional provisions for review and approval of nontank vessel plans. (Repealed)
0.4K chars
Notes 18 AAC 75.413 Eff. 11/27/2002, Register 164; repealed 9/4/2014, Register 211, October 2014 Authority:AS 46.03.020 AS 46.04.030 AS 46.04.055 AS 46.04.070 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most…
18 AAC 75-414 Procedures to apply for oil discharge prevention and contingency plans; owner or operator changes
0.7K chars
A change in the owner, operator, or name of the owner or operator of a facility or operation with an approved oil discharge prevention and contingency plan requires that the new owner or operator submit an application package as an amendment under 18 AAC 75.415. Notes 18 AAC 75.4…
18 AAC 75-415 Procedures to apply for oil discharge prevention and contingency plans; plan amendments
4.5K chars
(a) An application for approval of an amendment to an oil discharge prevention and contingency plan must be submitted in accordance with 18 AAC 75.408 and approved by the department, before a change to a plan may take effect, unless it is a routine plan update under (b) of this s…
18 AAC 75-420 Procedures to apply for oil discharge prevention and contingency plans; plan renewals
1.2K chars
(a) A plan holder must apply for renewal of the department's approval of an oil discharge prevention and contingency plan in accordance with 18 AAC 75.408. For submittals after October 16, 2016, the application must be submitted at least 180 days, or the number of days stated in …
18 AAC 75-421 Procedures to apply for streamlined oil discharge prevention and contingency plans
2.0K chars
(a) An application for approval of a new streamlined oil discharge prevention and contingency plan must be made on an application form supplied by the department. (b) An application for approval of an amendment to a streamlined plan must be submitted using an application form sup…
18 AAC 75-425 Oil discharge prevention and contingency plan contents (Repealed)
0.6K chars
Notes 18 AAC 75.425 Eff. 5/14/92, Register 122; am 9/25/93, Register 127; am 3/28/96, Register 137; am 4/4/97, Register 142; am 12/14/2002, Register 164; am 5/26/2004, Register 170; am 12/30/2006, Register 180; am 9/4/2014, Register 211, October 2014; am 3/23/2017, Register 221, …
18 AAC 75-426 Streamlined plan contents
6.9K chars
A streamlined plan application must contain the following information: (1) the name, address, and telephone number of the plan holder; (2) for each covered vessel, the (A) vessel's name, official number, and country of registry; (B) name and address of the owner; and (C) name and…
18 AAC 75-427 [Repealed]
0.4K chars
Notes 18 AAC 75.427 Eff. 11/27/2002, Register 164; repealed 3/23/2017, Register 221, April 2017 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More compariso…
18 AAC 75-428 Response planning facilitator
2.5K chars
(a) A response planning facilitator registered under 18 AAC 75.500 - 18 AAC 75.580 may submit a streamlined plan under 18 AAC 75.421 on behalf of a plan holder. A response planning facilitator may (1) act as an intermediary between the plan holder and one or more streamlined plan…
18 AAC 75-429 Equipment, training, personnel, and fuel transfer requirements for noncrude oil tank vessel or barge streamlined plans
2.1K chars
(a) A noncrude oil tank vessel or barge that has an approved streamlined plan must maintain the following equipment on board:(1) sorbent boom, not less than six times the length of the vessel and at least five inches in height, and equipment necessary to secure it; (2) a vessel c…
18 AAC 75-430 Response planning standards
2.4K chars
(a) Notwithstanding the response planning standards set out in 18 AAC 75.430 - 18 AAC 75.442, the plan must demonstrate the general procedures to clean up a discharge of any size, including the greatest possible discharge that could occur, subject to the provisions of AS 46.04.02…
18 AAC 75-432 Response planning standards for oil terminal facilities
3.3K chars
(a) For an oil terminal facility, the plan holder shall maintain or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and other resour…
18 AAC 75-433 Response planning standards for railroad tank cars
0.9K chars
For a railroad tank car, the plan holder shall maintain, or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and other resources to (…
18 AAC 75-434 Response planning standards for exploration or production facilities
5.9K chars
(a) For an exploration or production facility, the plan holder shall maintain or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and…
18 AAC 75-436 Response planning standards for crude oil pipelines
2.7K chars
(a) For a crude oil pipeline facility, the plan holder shall maintain or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and other r…
18 AAC 75-438 Response planning standards for crude oil tank vessels and barges
3.0K chars
(a) For a crude oil tank vessel or barge, the plan holder shall maintain or have available under contract within its region of operation, sufficient discharge containment, storage, transfer, and cleanup equipment, personnel, and other resources to (1) contain or control, and clea…
18 AAC 75-440 Response planning standards for noncrude oil tank vessels and barges
1.3K chars
(a) For a noncrude oil tank vessel or barge, the plan holder shall maintain or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and o…
18 AAC 75-441 Response planning standards for nontank vessels
1.5K chars
(a) For a nontank vessel, the plan holder shall maintain or have available under contract or membership agreement within the plan holder's region of operation, sufficient oil discharge containment and control equipment and shall maintain or have available under contract or member…
18 AAC 75-442 Response planning standards for multiple operations
0.7K chars
For a plan having multiple facility types that require an approved oil discharge prevention and contingency plan, the plan holder must plan to respond to a discharge of the applicable response planning standard volume for each separate facility type in the plan as established und…
18 AAC 75-443 Prevention credits for nontank vessels. (Repealed)
0.5K chars
Notes 18 AAC 75.443 Eff. 11/27/2002, Register 164; repealed 9/4/2014, Register 211, October 2014 Authority:AS 46.03.020 AS 46.04.030 AS 46.04.055 AS 46.04.065 AS 46.04.070 State regulations are updated quarterly; we currently have two versions available. Below is a comparison bet…
18 AAC 75-445 Approval criteria for oil discharge prevention and contingency plans (Repealed)
0.5K chars
Notes 18 AAC 75.445 Eff. 5/14/92, Register 122; am 9/25/93, Register 127; am 3/28/96, Register 137; am 4/4/97, Register 142; am 5/26/2004, Register 170; am 12/30/2006, Register 180; repealed 2/5/2023, Register 245, April 2023 State regulations are updated quarterly; we currently …
18 AAC 75-446 [Repealed]
0.4K chars
Notes 18 AAC 75.446 Eff. 11/27/2002, Register 164; am 4/16/2016, Register 218, July 2016 repealed 3/23/2017, Register 221, April 2017 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the p…
18 AAC 75-447 Department examination of new technologies (Repealed)
0.4K chars
Notes 18 AAC 75.447 Eff. 4/4/97, Register 142; repealed 2/5/2023, Register 245, April 2023 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison fea…
18 AAC 75-448 Oil discharge prevention and contingency plan; general plan requirements
2.7K chars
(a) An oil discharge prevention and contingency plan submitted for approval under 18 AAC 75.400 - 18 AAC 75.495 must be usable as a working plan for oil discharge control, containment, cleanup, and disposal. The plan must contain enough information, analyses, supporting data, and…
18 AAC 75-449 Part 1 - oil discharge prevention and contingency plan; Response Action Plan
15.6K chars
(a) The response action plan must include the following information in sufficient detail to clearly guide responders in an emergency event: (1) emergency action checklist - a short checklist of the immediate response and notification steps to be taken if an oil discharge occurs; …
18 AAC 75-450 Part 2 - oil discharge prevention and contingency plan; prevention plan
3.2K chars
(a) The prevention plan must demonstrate that the applicant meets all applicable requirements of 18 AAC 75.005 - 18 AAC 75.085 and must provide a detailed description of all oil discharge prevention measures, policies, and programs in place at the facility, with reference to the …
18 AAC 75-451 Part 3 - oil discharge prevention and contingency plan; supplemental information
19.9K chars
(a) The supplemental information section must provide the background and verification information identified in (b) - (n) of this section. (b) The plan holder must provide a facility description and operational overview. This is a general description of the oil storage, transfer,…
18 AAC 75-452 Part 4 - oil discharge prevention and contingency plan; best available technology review
5.6K chars
(a) Unless application of a state requirement would be preempted by federal law, the plan must provide for the use of best available technology consistent with the applicable criteria in (c) of this section. Technologies that are not subject to the response planning standards or …
18 AAC 75-453 Part 5 - oil discharge prevention and contingency plan; response planning standard
1.0K chars
The plan must (1) provide a mathematical calculation of the applicable response planning standards set out in 18 AAC 75.430 - 18 AAC 75.440 and 18 AAC 75.442; (2) include a detailed calculation and justification of reductions to the response planning standard; and (3) include an …
18 AAC 75-455 Department review procedures for oil discharge prevention and contingency plans; new plans, plan renewals, and major plan amendments
6.5K chars
(a) Not later than seven working days after receipt of an oil discharge prevention and contingency plan application package for a new plan, plan renewal or major amendment, the department will determine if the application package is sufficient for review. For an amendment applica…
18 AAC 75-456 Department decision on streamlined oil discharge prevention and contingency plans
2.1K chars
(a) The department will approve or disapprove a streamlined oil discharge prevention and contingency plan or plan amendment not later than five working days after receipt of a complete application. The department will approve a streamlined plan application submitted under 18 AAC …
18 AAC 75-457 Emergency modification of review process
1.2K chars
If, due to an emergency as described in AS 26.23, AS 46.04.080, or other applicable law, an applicant needs an expedited review, or if the commissioner or the commissioner's designee finds that an expedited review is necessary for the preservation of the public peace, health, saf…
18 AAC 75-459 Preissuance conference
1.4K chars
(a) After the department has determined that the application package is complete and before the department issues its decision under 18 AAC 75.460, the applicant may request a preissuance conference. The request must be made in writing, and will be granted if the applicant demons…
18 AAC 75-460 Department decision on oil discharge prevention and contingency plans; new plans, plan renewals, and major plan amendments
3.8K chars
(a) After considering the information, analyses, and commitments contained in a complete application package for approval of an oil discharge prevention and contingency plan and comments received not later than the close of the public comment period set out in 18 AAC 75.455, the …
18 AAC 75-465 Proof of approved plan
4.1K chars
(a) The owner or operator of an oil terminal facility may not cause or permit the transfer of oil to or from a vessel, barge, or railroad tank car unless (1) the operator of the vessel, barge, or railroad tank car has produced for inspection by the facility owner or operator the …