25,665 sections across 776 Alaska regulatory chapters.
20 AAC 25-022 Notice of ownership
0.6K chars
Within 15 days after a person becomes an owner of a property on which operations subject to this chapter are proposed to the commission or are being conducted, the person shall file a Notice of Ownership (Form 10-417). Notes 20 AAC 25.022 Eff. 4/2/86, Register 97; am 11/7/99, Reg…
20 AAC 25-025 Bonding
5.1K chars
(a) An operator proposing to drill a well for which a permit is required under 20 AAC 25.005 shall file a bond and, if required under (2) of this subsection, security to ensure that each well is drilled, operated, maintained, repaired, plugged and abandoned and each location is c…
20 AAC 25-026 Claims
0.6K chars
Commission approval of the abandonment of a well and the release of the bond required by 20 AAC 25.025 constitutes a presumption of proper abandonment, but does not relieve an operator of further claim by the commission after the abandonment. Notes 20 AAC 25.026 Eff. 4/13/80, Reg…
20 AAC 25-030 Casing and cementing
9.2K chars
(a) A complete proposed well casing and cementing program must be submitted with an application for a Permit to Drill (Form 10-401). Unless modified or altered by pool rules established under 20 AAC 25.520, a well casing and cementing program must be designed to (1) provide suita…
20 AAC 25-033 Primary well control for drilling: drilling fluid program and drilling fluid system
7.6K chars
(a) A drilling operation must be equipped with a drilling fluid system meeting the requirements of this section, unless the commission determines that a drilling fluid system is not necessary for primary well control. The operator shall submit with an application for a Permit to …
20 AAC 25-035 Secondary well control for primary drilling and completion: blowout prevention equipment and diverter requirements
19.5K chars
(a) This section applies to drilling and completion operations other than those covered by 20 AAC 25.036. These operations are also subject to the requirements of 20 AAC 25.527. (b) The operator shall submit the following information with the application for a Permit to Drill (Fo…
20 AAC 25-036 Secondary well control for through-tubing drilling and completion: blowout prevention equipment requirements
15.3K chars
(a) This section applies to drilling and completion operations performed through existing production tubing. These operations are also subject to the requirements of 20 AAC 25.527. (b) The operator shall submit the following information with the application for a Permit to Drill …
20 AAC 25-037 [Repealed]
0.4K chars
Notes 20 AAC 25.037 Eff. 11/7/99, Register 152; repealed 7/25/2020, Register 235, October 2020 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison…
20 AAC 25-040 Well identification
2.2K chars
(a) Every well must be identified by a sign posted in a conspicuous place. During the period of time from commencement of drilling operations to well completion, suspension, or abandonment, the sign must be on or near the drill rig, but not more than 100 feet from the well. After…
20 AAC 25-045 Sealing off strata (Repealed)
0.3K chars
Notes 20 AAC 25.045 Repealed 4/2/86. State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compar…
20 AAC 25-047 [Repealed]
0.4K chars
Notes 20 AAC 25.047 Eff. 4/2/86, Register 97; am 11/7/99, Register 152; repealed 7/25/2020, Register 235, October 2020 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly …
20 AAC 25-050 Wellbore surveys
5.7K chars
(a) A well that is not intentionally deviated must be(1) drilled as close to vertical as is possible using conventional drilling techniques, except that deviation is permitted for short intervals to straighten the hole, sidetrack junk, or correct mechanical difficulties; (2) surv…
20 AAC 25-055 Drilling units and well spacing
3.9K chars
(a) The commission will, in its discretion, establish drilling units to govern well spacing and prescribe a spacing pattern by pool rules adopted in accordance with 20 AAC 25.520. In the absence of an order by the commission establishing drilling units or prescribing a spacing pa…
20 AAC 25-061 Well site surveys
1.6K chars
(a) For an exploratory or stratigraphic test well, near surface strata to a depth of 2,000 feet in the vicinity of the well must be evaluated seismically by common depth point refraction or reflection profile analysis, or by another method approved by the commission, to identify …
20 AAC 25-065 Hydrogen sulfide
2.7K chars
(a) If hydrogen sulfide gas is encountered in excess of 20 ppm, the operator shall notify the commission within 24 hours after the encounter. (b) If a well is to be drilled in an area where a formation to be penetrated is known to contain hydrogen sulfide gas, or if hydrogen sulf…
20 AAC 25-066 Gas detection
4.6K chars
(a) Drilling and workover rigs must meet the following minimum requirements for methane and hydrogen sulfide gas detection: (1) the methane detection system must have a minimum of three sensing points; one sensing point must be under the substructure near the cellar, one must be …
20 AAC 25-070 Records and reports
2.2K chars
The operator of a well shall (1) keep a detailed accurate daily record of the actual drilling, completion, workover, repair, and plugging operations, and of the tests required by this chapter; the daily record must be available for inspection at reasonable times by the commission…
20 AAC 25-071 Logs and geologic data
4.7K chars
(a) An operator shall log the well from total depth to the base of conductor pipe by either a complete electrical or gamma-ray log unless the commission specifies the type of each log to be run. (b) Not later than 90 days after completion, suspension, or plugging of a well or wel…
20 AAC 25-072 Temporary shutdown of drilling or completion operations
2.5K chars
(a) If circumstances prevent the continuation of the program approved on a Permit to Drill (Form 10-401), or if an operator wishes to change drill rigs, the operator shall apply to the commission for approval to shut down drilling or completion operations temporarily. Based on th…
20 AAC 25-075 Other wells in designated areas
0.9K chars
There are areas in the state where drilling operations could unexpectedly encounter oil, gas, or hazardous substances at shallow depths. When the commission obtains sufficient evidence to define a specific area and the approximate depth range of the substances, it will issue an o…
20 AAC 25-080 Annular disposal of drilling waste
8.0K chars
(a) A person may not dispose of drilling waste through the annular space of a well unless authorized by the commission under this section. The operator of a well permitted under AS 31.05.090 may request authorization for the disposal of drilling waste through the well's annular s…
20 AAC 25-105 Abandonment of wells
3.4K chars
(a) All wells that have been permitted on a property under 20 AAC 25.005 must be abandoned before expiration of the owner's rights in that property or if, after notice and hearing, the commission orders abandonment for safety reasons or because the operator has effectively abando…
20 AAC 25-107 Plugging well branches
1.4K chars
(a) An operator may plug a well branch before abandoning or suspending the well. If a well branch has not been completed, the operator shall plug the well branch before removal of the drill rig, unless well operations are shut down in accordance with 20 AAC 25.072. (b) An Applica…
20 AAC 25-110 Suspended wells
8.5K chars
(a) If allowed under 20 AAC 25.105, an operator may apply to the commission under this section to approve the suspension of a well or to renew the approval of the suspension of a well. The operator must (1) state the reasons the well should be suspended, and why the well should n…
20 AAC 25-112 Well plugging requirements
8.9K chars
(a) Plugging of the uncased portion of a wellbore must be performed in a manner that ensures that all hydrocarbons and freshwater are confined to their respective indigenous strata and are prevented from migrating into other strata or to the surface. The minimum requirements for …
20 AAC 25-115 Shut-in wells
1.1K chars
(a) No later than March 31 of each year, an operator shall file with the commission a report on completed development or service wells that have been shut in for 365 days or longer as of January 1 of that year. The report must provide(1) the current known mechanical condition of …
20 AAC 25-120 Well abandonment marker
1.2K chars
The exact surface location of an abandoned onshore well must be shown by a well abandonment marker plate that (1) is constructed of steel that is at least 1/4 inch thick; (2) is welded to, and covers, the outermost casing string, including the conductor casing; (3) does not exten…
20 AAC 25-140 Water wells
1.4K chars
If a well drilled onshore for oil or gas is to be abandoned, but is safe for use as a freshwater well, a person who wishes to use the well as a freshwater well must obtain written authorization to do so from the landowner and the owner of the surface rights. The authorization mus…
20 AAC 25-170 Onshore location clearance
3.1K chars
(a) At or after the time that a well drilled onshore is abandoned and before the earlier of one year after well abandonment or the expiration of the owner's rights in the property, (1) the operator shall remove the wellhead equipment and casing to a depth at least three feet belo…
20 AAC 25-172 Offshore location clearance
3.5K chars
(a) No later than the time that all wells drilled from a fixed offshore platform are abandoned and the platform is removed or dismantled, the operator shall remove all well casing to a depth at least one foot below the mudline. The operator shall provide the commission with verif…
20 AAC 25-200 Production equipment
1.6K chars
(a) Surface production equipment must be installed to control, separate, clean, gather, and carry to the point of custody transfer or other disposition in a safe manner all produced oil, gas, and water. All equipment must be installed, operated, and maintained in accordance with …
20 AAC 25-205 Notification of uncontrolled release of oil or gas
1.2K chars
(a) The operator shall immediately notify the commission of any uncontrolled release exceeding 10 barrels of oil or 1,000 mscf of gas from a well or production handling operation or any uncontrolled release that results in a shutdown of operations at a production facility. (b) Wi…
20 AAC 25-210 Multiple completions of wells
1.0K chars
A well may not be completed in more than one pool without approval of the commission. The commission will require evidence of complete separation of flowstreams from separate pools, as ascertained by a pressure test or other acceptable test conducted at the time the packers are s…
20 AAC 25-215 Commingling of production and injection into two or more pools
1.6K chars
(a) On the surface, the production from one pool may not be commingled with that from another pool except if the quantities from each pool are determined by monthly well tests or by another method of determining pool production approved by the commission. (b) Commingling of produ…
20 AAC 25-225 [Repealed]
0.4K chars
Notes 20 AAC 25.225 Eff. 4/13/80, Register 74; am 4/2/86, Register 97; am 11/7/99, Register 152; repealed 7/25/2020, Register 235, October 2020 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version…
20 AAC 25-228 Production measurement equipment for custody transfer
5.2K chars
(a) Hydrocarbon production must be measured in accordance with this section before severance from the property or unit where produced. Crude oil sample collection, handling, and analysis in connection with production measurement must be performed in conformance with relevant part…
20 AAC 25-230 Measurement, allocation, and reporting of well production
1.3K chars
(a) Production from each well must be measured to determine the quantities of oil, gas, and water, using equipment and techniques acceptable to the commission as accurate and reliable. Production from a group of wells, property, or unit may be measured as a whole, if individual w…
20 AAC 25-235 Gas disposition
3.6K chars
(a) For each production facility the operator shall compile and report monthly gas disposition and acquisition on the Facility Report of Produced Gas Disposition (Form 10-422). If a facility's production comes from multiple pools, the operator shall allocate production between ea…
20 AAC 25-240 Gas-oil ratio limitations
1.3K chars
(a) An oil well may not be produced if the gas-oil ratio of the well exceeds the original solution gas-oil ratio of the crude within the producing pool by more than 100 percent. (b) Upon written application by an operator, the commission will, in its discretion, waive the limitat…
20 AAC 25-245 [Repealed]
0.4K chars
Notes 20 AAC 25.245 Eff. 4/13/80, Register 74; am 4/2/86, Register 97; am 11/7/99, Register 152; repealed 7/25/2020, Register 235, October 2020 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version…
20 AAC 25-250 Disposal of salt water and other wastes (Repealed)
0.3K chars
Notes 20 AAC 25.250 Repealed 4/2/86. State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compar…
20 AAC 25-252 Underground disposal of oil field wastes and underground storage of hydrocarbons
6.8K chars
(a) The underground disposal of oil field wastes and the underground storage of hydrocarbons are prohibited except as ordered by the commission under this section. In response to a letter of application for injection filed by an operator, the commission will issue an order author…
20 AAC 25-255 Equitable distribution of production (Repealed)
0.3K chars
Notes 20 AAC 25.255 Repealed 4/2/86. State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compar…
20 AAC 25-260 [Repealed]
0.4K chars
Notes 20 AAC 25.260 Eff. 4/13/80, Register 74; am 4/2/86, Register 97; repealed 7/25/2020, Register 235, October 2020 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly r…
20 AAC 25-265 Well safety valve systems
15.8K chars
(a) A completed well must be equipped with a functional safety valve system unless the well is (1) a water source well; (2) a disposal injection well; (3) an observation well; (4) shut-in; or (5) suspended. (b) A safety valve system must have a surface safety valve with an actuat…
20 AAC 25-270 Reservoir properties
1.8K chars
(a) The operator shall determine the initial reservoir pressure in each new pool before regular production. The results must be reported to the commission on a Reservoir Pressure Report (Form 10-412). (b) The operator shall obtain fluid samples from each new pool at the time of d…
20 AAC 25-275 Reservoir fluid properties (Repealed)
0.4K chars
Notes 20 AAC 25.275 Eff. 4/2/86, Register 97; repealed 11/7/99, Register 152 Effective 11/7/99, Register 152, the substance of 20 AAC 25.275 was relocated to 20 AAC 25.270. State regulations are updated quarterly; we currently have two versions available. Below is a comparison be…
20 AAC 25-280 Workover operations
3.4K chars
(a) An Application for Sundry Approvals (Form 10-403) must be submitted to and approved by the commission in order to enter a well and conduct one or more of the following types of well workover operations:(1) the perforation or reperforation of casing; (2) stimulation; (3) the p…
20 AAC 25-283 Hydraulic fracturing
21.5K chars
(a) Before hydraulic fracturing, the operator must submit an Application for Sundry Approvals (Form 10-403) under 20 AAC 25.280. Unless modified or altered by pool rules established under 20 AAC 25.520, the application must include (1) an affidavit stating that all owners, landow…
20 AAC 25-285 Secondary well control for tubing workover operations: blowout prevention equipment requirements
13.0K chars
(a) This section applies to workover operations performed with the tree removed. These operations are also subject to the requirements of 20 AAC 25.527. (b) The rated working pressure of the BOPE and other well control equipment must exceed the maximum potential surface pressure …