Ark. Code Ann. § 23-18-1419 — under Light, Heat, and Power Utilities.

Ark. Code Ann. § 23-18-1419

(a) The Arkansas Public Service Commission shall promulgate rules to implement and administer this subchapter.

(b) Rules that the commission shall promulgate under this subchapter include without limitation rules relating to:(1) Requirements and terms for a permit for the construction, operation, or redevelopment of a wind energy facility or a wind energy facility expansion;(2) Requirements for an application for a permit for the construction, operation, or redevelopment of a wind energy facility or a wind energy facility expansion;(3) Requirements for a renewal application for a permit for the construction, operation, or redevelopment of a wind energy facility or a wind energy facility expansion; and(4) The erection, construction, reconstruction, change, alteration, maintenance, use, operation, and decommissioning of wind energy facilities, including without limitation the:(A) Interconnection of power lines with regional transmission organizations, independent transmission system operators, or similar organizations; and(B) Establishment of necessary cooperation for site visits and enforcement investigations.

(1) Requirements and terms for a permit for the construction, operation, or redevelopment of a wind energy facility or a wind energy facility expansion;

(2) Requirements for an application for a permit for the construction, operation, or redevelopment of a wind energy facility or a wind energy facility expansion;

(3) Requirements for a renewal application for a permit for the construction, operation, or redevelopment of a wind energy facility or a wind energy facility expansion; and

(4) The erection, construction, reconstruction, change, alteration, maintenance, use, operation, and decommissioning of wind energy facilities, including without limitation the:(A) Interconnection of power lines with regional transmission organizations, independent transmission system operators, or similar organizations; and(B) Establishment of necessary cooperation for site visits and enforcement investigations.

(A) Interconnection of power lines with regional transmission organizations, independent transmission system operators, or similar organizations; and

(B) Establishment of necessary cooperation for site visits and enforcement investigations.