34 chapters · 998 sections in this title.
Ark. Code Ann. § 19-70-101 Title
0.1K chars
This chapter shall be known and may be cited as the “Construction Manager-General Contractor Method of Procurement Program”.
Ark. Code Ann. § 19-70-102 Legislative findings
3.1K chars
(1) The General Assembly finds that:(1) An efficient transportation system is critical for Arkansas's economy and the quality of life of the state's residents;(2) Transportation projects are costly and the revenues currently available for highways and local roads are inadequate t…
Ark. Code Ann. § 19-70-103 Definitions
6.8K chars
(1) As used in this chapter:(1) “Authorized contingency” means a provision prepared and submitted by the construction manager-general contractor as part of the guaranteed maximum price that is designed to cover costs that may result from:(A) Incomplete design;(B) Unforeseen and u…
Ark. Code Ann. § 19-70-104 Rules
0.1K chars
The State Highway Commission and the Arkansas Department of Transportation may promulgate rules to implement and administer this chapter.
Ark. Code Ann. § 19-70-201 Construction Manager-General Contractor Method of Procurement Program — Creation
0.4K chars
(a) The State Highway Commission may develop a Construction Manager-General Contractor Method of Procurement Program. (b) The commission may use the Construction Manager-General Contractor Method of Procurement Program for any transportation project for which the construction cos…
Ark. Code Ann. § 19-70-202 Project selection
0.4K chars
If the Arkansas Department of Transportation determines that a construction manager-general contractor method of procurement is appropriate for a transportation project, the department shall establish a procedure for awarding the contract for construction of the construction mana…
Ark. Code Ann. § 19-70-203 Request for proposals
5.5K chars
(a) A request for proposals under this chapter shall include without limitation the following:(1) The minimum qualifications of the construction manager-general contractor;(2) The procedures for submitting a proposal to the Arkansas Department of Transportation, the criteria for …
Ark. Code Ann. § 19-70-204 Construction manager-general contractor selection
4.8K chars
(a) The Arkansas Department of Transportation shall:(1) Prepare contract plans, specifications, special provisions, and other requirements composing the contract for construction of a transportation project elected for procurement using the construction manager-general contract m…