The PSA work plan and PSA report shall be signed and notarized by the contractor responsible for the completion of the preliminary site assessment and by a certified industrial hygienist for sufficiency and completeness.
Health & Safety Code § 25400.38 — under California Health & Safety Code.
Health & Safety Code § 25400.38
The PSA work plan and PSA report shall be signed and notarized by the contractor responsible for the completion of the preliminary site assessment and by a certified industrial hygienist for sufficiency and completeness.