Section 8414

Civ. Code § 8414 — under California Civ. Code.

Civ. Code § 8414

A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times:

(a) After the claimant ceases to provide work.

(b) Before the earlier of the following times:

(1) Ninety days after completion of the work of improvement.

(2) Thirty days after the owner records a notice of completion or cessation.