Civ. Code § 8502 Section 8502
0.4K chars
(a) A stop payment notice shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1, and shall be signed and verified by the claimant. (b) The notice shall include a general description of work to be provided, and an estimate of the total amount in…
Civ. Code § 8504 Section 8504
0.3K chars
A claimant that willfully gives a false stop payment notice or that willfully includes in the notice a demand to withhold for work that has not been provided forfeits all right to participate in the distribution of the funds withheld and all right to a lien under Chapter 4 (comme…
Civ. Code § 8506 Section 8506
0.5K chars
(a) A stop payment notice to an owner shall be given to the owner or to the owner’s architect, if any. (b) A stop payment notice to a construction lender holding construction funds shall not be effective unless given to the manager or other responsible officer or person at the of…
Civ. Code § 8508 Section 8508
0.4K chars
A stop payment notice is not valid unless both of the following conditions are satisfied: (a) The claimant gave preliminary notice to the extent required by Chapter 2 (commencing with Section 8200). (b) The claimant gave the stop payment notice before expiration of the time withi…
Civ. Code § 8510 Section 8510
0.6K chars
(a) A person may obtain release of funds withheld pursuant to a stop payment notice by giving the person withholding the funds a release bond. (b) A release bond shall be given by an admitted surety insurer and shall be conditioned for payment of any amount not exceeding the pena…
Civ. Code § 8520 Section 8520
0.6K chars
(a) A person that has a lien right under Chapter 4 (commencing with Section 8400), other than a direct contractor, may give the owner a stop payment notice. (b) The owner may give notice, in compliance with the requirements of Chapter 2 (commencing with Section 8100) of Title 1, …
Civ. Code § 8522 Section 8522
0.8K chars
(a) Except as provided in subdivision (b), on receipt of a stop payment notice an owner shall withhold from the direct contractor or from any person acting under authority of a direct contractor a sufficient amount due or to become due to the direct contractor to pay the claim st…
Civ. Code § 8530 Section 8530
0.1K chars
A person that has a lien right under Chapter 4 (commencing with Section 8400) may give a construction lender a stop payment notice.
Civ. Code § 8532 Section 8532
0.6K chars
A claimant may give a construction lender a stop payment notice accompanied by a bond in an amount equal to 125 percent of the amount of the claim. The bond shall be conditioned that if the defendant recovers judgment in an action to enforce payment of the claim stated in the sto…
Civ. Code § 8534 Section 8534
0.7K chars
(a) A construction lender that objects to the sufficiency of sureties on the bond given with a bonded stop payment notice shall give notice to the claimant of the objection, within 20 days after the bonded stop payment notice is given. The notice shall comply with the requirement…
Civ. Code § 8536 Section 8536
0.6K chars
(a) Except as provided in subdivision (b), on receipt of a stop payment notice a construction lender shall withhold from the borrower or other person to whom the lender or the owner is obligated to make payments or advancement out of the construction fund sufficient funds to pay …
Civ. Code § 8538 Section 8538
1.2K chars
(a) The claimant may make a written request for notice of an election by the construction lender under Section 8536 not to withhold funds. The request shall be made at the time the claimant gives the construction lender the stop payment notice and shall be accompanied by a preadd…
Civ. Code § 8540 Section 8540
1.0K chars
(a) Funds withheld pursuant to a stop payment notice shall be distributed in the following order of priority: (1) First, to pay claims of persons that have given a bonded stop payment notice. If funds are insufficient to pay the claims of those persons in full, the funds shall be…
Civ. Code § 8542 Section 8542
0.8K chars
Notwithstanding Section 8540: (a) If funds are withheld pursuant to a stop payment notice given to a construction lender by a direct contractor or subcontractor, the direct contractor or subcontractor may recover only the net amount due the direct contractor or subcontractor afte…
Civ. Code § 8544 Section 8544
0.3K chars
The rights of a claimant who gives a construction lender a stop payment notice are not affected by an assignment of construction loan funds made by the owner or direct contractor, and the stop payment notice has priority over the assignment, whether the assignment is made before …
Civ. Code § 8550 Section 8550
1.1K chars
(a) A claimant shall commence an action to enforce payment of the claim stated in a stop payment notice at any time after 10 days from the date the claimant gives the stop payment notice. (b) A claimant shall commence an action to enforce payment of the claim stated in a stop pay…
Civ. Code § 8552 Section 8552
0.4K chars
If more than one claimant has given a stop payment notice: (a) Any number of claimants may join in the same enforcement action. (b) If claimants commence separate actions, the court first acquiring jurisdiction may order the actions consolidated. (c) On motion of the owner or con…
Civ. Code § 8554 Section 8554
0.3K chars
Notwithstanding Section 583.420 of the Code of Civil Procedure, if an action to enforce payment of the claim stated in a stop payment notice is not brought to trial within two years after commencement of the action, the court may in its discretion dismiss the action for want of p…
Civ. Code § 8556 Section 8556
0.4K chars
A stop payment notice ceases to be effective, and a person withholding funds pursuant to the notice shall release them, in either of the following circumstances: (a) An action to enforce payment of the claim stated in the stop payment notice is dismissed, unless expressly stated …
Civ. Code § 8558 Section 8558
0.9K chars
(a) In an action to enforce payment of the claim stated in a bonded stop payment notice, the prevailing party is entitled to a reasonable attorney’s fee in addition to costs and damages. (b) The court, on notice and motion by a party, shall determine who is the prevailing party o…
Civ. Code § 8560 Section 8560
0.3K chars
If the claimant is the prevailing party in an action to enforce payment of the claim stated in a bonded stop payment notice, any amount awarded on the claim shall include interest at the legal rate calculated from the date the stop payment notice is given.