Pub. Res. Code § 25540.5 Section 25540.5
1.8K chars
The commission may, at the petition of a county which has adopted a geothermal element for its general plan, approve an equivalent certification program which delegates to that county full authority for the certification of all geothermal powerplants within such county. Once appr…
Pub. Res. Code § 25540.6 Section 25540.6
2.3K chars
(a) Notwithstanding any other provision of law, no notice of intention is required, and the commission shall issue its final decision on the application, as specified in Section 25523, within 12 months after the filing of the application for certification of the powerplant and re…
Pub. Res. Code § 25541 Section 25541
0.5K chars
The commission may exempt from this chapter thermal powerplants with a generating capacity of up to 100 megawatts and modifications to existing generating facilities that do not add capacity in excess of 100 megawatts, if the commission finds that no substantial adverse impact on…
Pub. Res. Code § 25541.1 Section 25541.1
1.0K chars
It is the intent of the Legislature to encourage the development of thermal powerplants using resource recovery (waste-to-energy) technology. Previously enacted incentives for the production of electrical energy from nonfossil fuels in commercially scaled projects have failed to …