Pub. Cont. Code § 20405 Section 20405
3.2K chars
(a) The board shall afford all bidders an opportunity to examine the plans, specifications, and working details, and shall award the contract to the lowest responsible bidder. The board may provide by resolution that the bids be opened, examined, and declared by an officer design…
Pub. Cont. Code § 20406 Section 20406
0.5K chars
If the board of supervisors is advised by the county surveyor or, in a county not having a county surveyor, by the officer having similar duties and authority, that the work can be done for a sum less than the lowest responsible bid, the board may reject all bids and order the wo…
Pub. Cont. Code § 20407 Section 20407
0.8K chars
In the event of great emergency, including, but not limited to, states of disaster defined in Section 8558 of the Government Code, upon the majority vote of the board, the board may proceed at once to replace or repair any and all bridges without adopting plans, specifications, s…
Pub. Cont. Code § 20409 Section 20409
0.5K chars
The board of supervisors may authorize such road commissioner to employ such workmen and purchase such materials, equipment, tools, and appliances and cause such work to be done as is necessary to construct or maintain such bridges and to keep them in repair without adopting plan…
Pub. Cont. Code § 20410 Section 20410
0.3K chars
The provisions of this article shall apply to contracts by legislative bodies for the doing of work or the furnishing of materials, supplies and equipment, as provided for in the Improvement Act of 1911, Division 7 (commencing with Section 5000) of the Streets and Highways Code.
Pub. Cont. Code § 20411 Section 20411
0.2K chars
Before the legislative body awards any contract for doing any work or for furnishing materials, supplies and equipment or any portion thereof, authorized by this division, the legislative body shall pass a resolution ordering the work.
Pub. Cont. Code § 20412 Section 20412
0.7K chars
Notice shall be posted inviting sealed proposals or bids for doing such work, or for furnishing materials, supplies and equipment or any portion thereof. Notice inviting such proposals, and referring to the specifications on file, shall be published, but if there is no newspaper …
Pub. Cont. Code § 20413 Section 20413
0.8K chars
All bids for construction work shall be presented under sealed cover and shall be accompanied by one of the following forms of bidder’s security: (a) Cash. (b) A cashier’s check made payable to the city. (c) A certified check made payable to the city. (d) A bidder’s bond executed…
Pub. Cont. Code § 20414 Section 20414
0.9K chars
The proposals or bids shall be delivered to the clerk, or any other officer designated by the legislative body, and the legislative body shall, in open session publicly open, examine and declare the same. If the legislative body by resolution so provides the proposals or bids may…
Pub. Cont. Code § 20415 Section 20415
0.6K chars
The legislative body may reject any and all proposals or bids should it deem this for the public good, and also the bid of any party who has been delinquent or unfaithful in any former contract with the city, and shall reject all proposals or bids other than the lowest regular pr…
Pub. Cont. Code § 20416 Section 20416
0.5K chars
Whenever the total amount bid by the lowest responsible bidder plus the estimated amount of incidental costs would result in assessments under this division which exceed by more than 15 percent the engineer’s estimate of cost of the proposed work to be assessed, as stated in the …
Pub. Cont. Code § 20417 Section 20417
0.3K chars
If the bids are rejected or no bids are received the legislative body may readvertise for proposals or bids for the performance of the work as in the first instance, without further proceedings, and thereafter proceed in the manner provided in this chapter.
Pub. Cont. Code § 20418 Section 20418
0.7K chars
The check or bond accompanying any proposal or bid which is accepted shall be held by the clerk until the contract for doing the work has been entered into, either by the lowest bidder or by the owners of three-fourths part of the frontage, whereupon the certified check or bond s…
Pub. Cont. Code § 20419 Section 20419
1.1K chars
If any local, state or national agency or authority contributes the labor, or labor and any portion of the materials, supplies or equipment necessary for the construction of any improvement authorized under this division, the contract shall be for only those items which are not c…
Pub. Cont. Code § 20420 Section 20420
2.4K chars
Notice of the award of the contract shall be published by the clerk. The clerk shall, upon payment of the statutory fee prescribed therefor, record a notice of the award of contract in the office of the county recorder. Said recordation shall constitute notice to all persons that…
Pub. Cont. Code § 20421 Section 20421
0.6K chars
The owners of three-fourths of the area of lands liable to be assessed, or their agents (who shall make oath that they are the owners or agents) are not required to present sealed proposals or bids, but may within 10 days after the first publication, or first posting if there is …
Pub. Cont. Code § 20422 Section 20422
0.4K chars
If the owners fail to elect to take the work, and to enter into a written contract therefor within 10 days, or to commence the work within 15 days after the date of the written contract, and to prosecute the work with diligence to completion, the superintendent of streets shall e…
Pub. Cont. Code § 20423 Section 20423
0.4K chars
If the original bidder neglects, fails or refuses, for 25 days after the first publication of the notice of the award of the contract, to enter into the contract, the legislative body, without further proceedings, shall again advertise for and receive proposals or bids, as in the…
Pub. Cont. Code § 20424 Section 20424
0.3K chars
If no bids are received in response to this second call for bids, the legislative body may again advertise for and receive bids under the same proceedings at any time and let the contract to the then lowest bidder, and such delay shall in no way affect the validity of any of the …
Pub. Cont. Code § 20425 Section 20425
0.2K chars
The bids of all persons and the election of all owners who have previously failed to enter into the contract shall be rejected in any bidding or election subsequent to the first for the same work.
Pub. Cont. Code § 20426 Section 20426
0.3K chars
All contractors, contracting owners included, shall, at the time of executing any contract for the work, execute a bond to the satisfaction and approval of the superintendent of streets and payable to the city, in a sum not less than 25 percent of the amount of the contract, cond…
Pub. Cont. Code § 20427 Section 20427
1.4K chars
At any time prior to publication and posting notice inviting bids, the legislative body by resolution, may determine that if the contractor, contracting owners included, does not complete the work within the time limit specified in the contract or within the further time that the…
Pub. Cont. Code § 20428 Section 20428
0.9K chars
If the owner or contractor who may have taken any contract does not complete the work within the time limited in the contract, or within such further time as the legislative body may give him, or abandons or fails to proceed with the work, the legislative body may declare him in …
Pub. Cont. Code § 20429 Section 20429
1.2K chars
Before being entitled to a contract, the bidder to whom the award was made, or the owners who have elected to take the contract, must advance to the superintendent of streets, for payment by him, the cost of publication of the notices, resolutions, orders and matters required und…
Pub. Cont. Code § 20430 Section 20430
0.5K chars
If the work is abandoned by the city before work is actually started or before any materials, supplies or equipment have been furnished or used, the incidental expenses incurred previous to such abandonment shall be paid out of the city treasury, but such expense for which the ci…
Pub. Cont. Code § 20431 Section 20431
0.5K chars
At any time within 10 days from the date of the first publication of the notice of award of the contract, any owner of, or other persons having any interest in, any lot or land liable to assessment, who claims that any of the previous acts or proceedings relating to the work are …
Pub. Cont. Code § 20432 Section 20432
0.3K chars
All objections to any act or proceeding occurring prior to the time within which such objections are permitted to be filed in relation to the work, not made in writing and in the manner and at the time specified, shall be waived, if the resolution of intention to do the work has …
Pub. Cont. Code § 20433 Section 20433
0.2K chars
If in the opinion of the legislative body the public interest will not be served by allowing the property owners to take the contract it may so provide in the resolution of intention.
Pub. Cont. Code § 20434 Section 20434
0.7K chars
An action to determine the validity of proceedings relating to the work and the validity of any contract entered or to be entered into pursuant thereto may be brought by the legislative body or by the contractor pursuant to Chapter 9 (commencing with Section 860) of Title 10 of P…
Pub. Cont. Code § 20435 Section 20435
0.2K chars
In such action, all findings, conclusions and determinations of the legislative body which conducted the proceedings shall be conclusive in the absence of actual fraud.
Pub. Cont. Code § 20436 Section 20436
0.8K chars
If an action is commenced under the provisions of this chapter to determine the validity of any contract or proposed contract, and the contract has not been signed, the contractor shall not be obligated to sign the same until a judgment sustaining the validity of the proceedings …
Pub. Cont. Code § 20436.5 Section 20436.5
0.2K chars
Notwithstanding any other provisions of law, the action authorized by this chapter shall not be brought by any person other than the legislative body or the contractor, nor shall the action be brought after the date fixed for the beginning of work.
Pub. Cont. Code § 20437 Section 20437
0.3K chars
The superintendent of streets is hereby authorized in his official capacity to make all written contracts, and to receive all bonds authorized by this division and to do any other act, either expressly or impliedly required by this division, that pertains to the street department…
Pub. Cont. Code § 20438 Section 20438
0.3K chars
He shall fix the time for the commencement, which shall not be more than 45 days from the date of the contract, and for the completion of the work under each contract entered into by him. The work shall be prosecuted with diligence from day to day thereafter to completion.
Pub. Cont. Code § 20439 Section 20439
0.7K chars
He may extend the time fixed for completion of the work from time to time, under the direction of the legislative body. All applications for extensions of time, if in writing, must be filed in the office of the clerk before the expiration of the original time fixed in the contrac…
Pub. Cont. Code § 20440 Section 20440
0.7K chars
The work, in all cases, shall be done under the direction and to the satisfaction of the superintendent of streets and the materials used shall comply with the specifications and be to the satisfaction of the superintendent of streets and all contracts made therefor shall contain…
Pub. Cont. Code § 20441 Section 20441
0.3K chars
The legislative body also may by resolution adopted within 10 days after the passage of the resolution ordering the work provide and direct that the assessment thereafter to be made in the proceeding shall be made and signed by the engineer instead of by the superintendent of str…
Pub. Cont. Code § 20442 Section 20442
0.3K chars
The contract shall contain express notice that, in no case, except where it is otherwise provided by law or by charter will the city, or any officer thereof, be liable for any portion of the expense, nor for any delinquency of persons or property assessed.
Pub. Cont. Code § 20443 Section 20443
0.5K chars
The legislative body may, by ordinance, prescribe general rules directing the superintendent of streets or the engineer, as the case may be, and the contractor as to the materials to be used, and the mode of executing the work, under all contracts thereafter made. The assessment …
Pub. Cont. Code § 20444 Section 20444
0.3K chars
If any fiscal agent of the United States government contributes any money or materials to be used in the construction of any work provided for in this division, the requirements of the agency contributing such money or materials may be incorporated in the contract.
Pub. Cont. Code § 20445 Section 20445
0.8K chars
If a contribution of labor or of labor and any portion of materials, supplies or equipment is to be made by any local, state or national agency or authority, the contract shall contain a provision that the legislative body may cancel the order for any undelivered materials, suppl…
Pub. Cont. Code § 20446 Section 20446
0.1K chars
“Changes” as used in this chapter shall include corrections, alterations, modifications, additions, omissions, increases or decreases.
Pub. Cont. Code § 20447 Section 20447
0.9K chars
Unless the power to proceed shall have ceased at the conclusion of the hearing on the resolution of intention because of a majority protest, at any time before the confirmation of the assessment the legislative body may make changes in, to or from the boundaries of the proposed a…
Pub. Cont. Code § 20448 Section 20448
0.4K chars
At the hearing on the resolution of intention, the legislative body, without further notice and hearing, may order any changes, as defined in Sections 20446 and 20447, except changes to include additional territory in the assessment district. Any changes to include additional ter…
Pub. Cont. Code § 20449 Section 20449
1.8K chars
Before ordering any changes made, the legislative body shall adopt a resolution briefly describing the changes proposed to be made, stating the amount of the estimated increase or decrease in the cost of the work by reason of the proposed changes and giving notice of a time and p…
Pub. Cont. Code § 20450 Section 20450
0.5K chars
If a resolution required under Section 20449 proposes to include additional territory in the assessment district, at least 15 days prior to the hearing fixed therein, the clerk shall mail a copy of the resolution to all persons owning real property within the additional territory…
Pub. Cont. Code § 20451 Section 20451
1.1K chars
Written objections to the proposed changes may be filed with the clerk by any interested person at any time not later than the time set for the hearing. The legislative body shall hear and pass upon the objections at the time appointed, or at any time to which the hearing thereof…
Pub. Cont. Code § 20452 Section 20452
0.7K chars
(a) No changes, except as provided in Section 20453, shall be made pursuant to this chapter that will increase the estimated assessable cost by more than 20 percent of the total estimated cost of the work as determined from either of the following: (1) The engineer’s estimate, if…
Pub. Cont. Code § 20453 Section 20453
0.2K chars
Changes may exceed the 20-percent limitation in cost when the legislative body orders such changes. That portion of the added cost which exceeds the 20-percent limitation shall be paid by the city.
Pub. Cont. Code § 20454 Section 20454
0.1K chars
Any changes made pursuant to this chapter shall not release or discharge the sureties upon any bond required under this division.