371 chapters · 7,566 sections in this title.
Pub. Util. Code § 26212 Section 26212
0.6K chars
If the proposition submitted at a special bond election fails to receive the requisite number of votes, the board shall not within six months after the election hold another special election for the submission of a proposition of incurring a bonded indebtedness substantially the …
Pub. Util. Code § 2801 Section 2801
0.8K chars
The Legislature hereby finds and declares that in order to promote the more rapid development of new sources of natural gas and electric energy, to maintain the economic vitality of the state through the continuing production of goods and the employment of its people, and to prom…
Pub. Util. Code § 2802 Section 2802
0.8K chars
“Private energy producer” includes every person, corporation, city, county, district, and public agency of the state generating or producing electricity not generated from conventional sources or natural gas for energy either directly or as a byproduct solely for his or its own u…
Pub. Util. Code § 2803 Section 2803
0.4K chars
“Interconnection” means the facilities necessary to physically connect the energy source of and the point of use by a private energy producer with the existing transmission facilities of a public utility, and shall include any necessary transformation, compression or other facili…