Factors to be considered

Colo. Rev. Stat. § 30-20-104, under Government - County.

Colo. Rev. Stat. § 30-20-104

(1) In considering an application for a proposed solid wastes disposal site and facility, the governing body having jurisdiction shall take into account:

(a) The effect that the solid wastes disposal site and facility will have on the surrounding property, taking into consideration the types of processing to be used, surrounding property uses and values, and wind and climatic conditions;

(b) The convenience and accessibility of the solid wastes disposal site and facility to potential users;

(c) The ability of the applicant to comply with the health standards and operating procedures provided for in this part 1 and such rules and regulations as may be prescribed by the department;

(d) Recommendations by county, district, or municipal public health agencies.

(2) Except as provided in this part 1, designation of approved solid wastes disposal sites and facilities shall be discretionary with the governing body having jurisdiction, subject to judicial review by the district court of appropriate jurisdiction.

(3) (a) Prior to the issuance of a certificate of designation, the governing body having jurisdiction shall require that the report, which shall be submitted by the applicant under section 30-20-103, be reviewed and a recommendation as to approval or disapproval be made by the department and shall be satisfied that the proposed solid wastes disposal site and facility conforms to the local government's comprehensive land use plan and zoning restrictions, if any. Any technical conditions of approval made by the department in its final report shall be incorporated as requirements in the certificate of designation. The application, report of the department, comprehensive land use plan, relevant zoning ordinances, and other pertinent information shall be presented to the governing body having jurisdiction at a public hearing to be held after notice. Such notice shall contain the time and place of the hearing, shall state that the matter to be considered is the applicant's proposal for a solid wastes disposal site and facility, shall provide a description of such proposed site and facility, and shall provide a description of the geographic area that is within three miles of such proposed site and facility. The notice shall be published in a newspaper having general circulation in the county or municipality in which the proposed solid wastes disposal site and facility is located at least ten but no more than thirty days prior to the date of the hearing. In addition, the notice of such public hearing shall be posted at a conspicuous point in at least one location at the offices of the governing body having jurisdiction and in at least one location at the proposed site. Such notice shall be posted for a period beginning at least thirty days before the public hearing and continuing through the date of such hearing.

(b) At the public hearing held pursuant to the provisions of this subsection (3), the governing body shall hear any written or oral testimony presented by governmental entities and residents concerning such proposed site or facility. All such testimony shall be considered by the governing body having jurisdiction in making a decision concerning such application. For the purposes of this subsection (3), residents means all individuals who reside within the geographic area controlled by the governing body having jurisdiction or within three miles of the proposed site and facility or who own property which lies within three miles of such proposed site and facility without regard to which county or municipality such individuals reside within.

Source: L. 67: p. 760, � 4. C.R.S. 1963: � 36-23-4. L. 71: p. 341, � 5. L. 91: Entire section amended, p. 966, � 6, effective June 5. L. 98: (3)(a) amended, p. 881, � 7, effective July 1. L. 2010: (1)(d) amended, (HB 10-1422), ch. 419, p. 2119, � 164, effective August 11.

30-20-104.5. Closure and postclosure care estimates - corrective action cost estimates - financial assurance requirements - rules. (1) The solid and hazardous waste commission shall promulgate rules that implement financial assurance requirements for the final closure of solid wastes disposal sites and facilities, the conduct of postclosure care for such sites and facilities, and the undertaking of any corrective action made necessary by the migration of contaminants from such sites and facilities into groundwater. Such rules shall include, but are not limited to, the following requirements:

(a) That the owner or operator of any solid wastes disposal site and facility shall maintain:

(I) A detailed written estimate of the cost of hiring a third party to close the largest area of such site and facility which has or will require a cover during the active life of such site and facility; and

(II) A detailed written estimate of the cost of hiring a third party to conduct postclosure care at such site and facility;

(b) That the owner or operator of any solid wastes disposal site and facility that is required to undertake a corrective action program pursuant to the requirements of subpart E of the federal regulations promulgated pursuant to the provisions of subtitle D of the federal Resource Conservation and Recovery Act of 1976, as amended, shall maintain a detailed written estimate of the cost of hiring a third party to perform such corrective action;

(c) That the owner or operator of any solid wastes disposal site and facility shall notify the department when the cost estimates required by paragraphs (a) and (b) of this subsection (1) have been placed in the operating file for such site and facility;

(d) That the owner or operator of any solid wastes disposal site and facility shall:

(I) Express the cost estimates required by paragraphs (a) and (b) of this subsection (1) in current dollars;

(II) Annually adjust such cost estimates to account for inflation; and

(III) Increase such cost estimates under the following circumstances:

(A) The cost estimate for the cost of hiring a third party to close such site and facility maintained pursuant to the provisions of subparagraph (I) of paragraph (a) of this subsection (1) shall be increased if changes to the closure plan for such site and facility or changes in the conditions of such site and facility increase the maximum cost of closure at any time during the remaining active life of such site and facility.

(B) The cost estimate for the cost of hiring a third party to conduct postclosure care for such site and facility maintained pursuant to the provisions of subparagraph (II) of paragraph (a) of this subsection (1) shall be increased if changes to the postclosure plan for such site and facility or changes in the conditions of site and facility increase the maximum cost of postclosure care for such site and facility.

(C) The cost estimate, if any, for the cost of hiring a third party to undertake corrective action for such site and facility maintained pursuant to the provisions of paragraph (b) of this subsection (1) shall be increased if changes in the corrective action program for such site and facility or changes in the conditions of such site and facility increase the maximum cost of corrective action for such site and facility.

(e) That the owner or operator of any solid wastes disposal site and facility shall comply with the financial assurance requirements mandated by the rules of the solid and hazardous waste commission promulgated pursuant to subsection (3) of this section.

(2) The owner or operator of a solid wastes disposal site and facility may reduce the amount of a cost estimate maintained pursuant to the provisions of paragraph (a) or (b) of subsection (1) of this section if such cost estimate exceeds the maximum cost of completing the actions contemplated by such cost estimate.

(3) (a) The solid and hazardous waste commission shall promulgate rules that require the owner or operator of a solid wastes disposal site and facility to establish sufficient financial assurance to pay for the cost estimates required by paragraphs (a) and (b) of subsection (1) of this section. No solid wastes disposal site and facility shall operate without being in compliance with the financial assurance requirements contained in such rules. Such rules shall include, but shall not be limited to, provisions that define the mechanisms that may be used by the owner or operator of a solid wastes disposal site and facility to establish sufficient financial assurance pursuant to this section. The mechanisms to establish financial assurance that are defined by the commission shall include, but are not limited to, those mechanisms authorized by the federal regulations promulgated pursuant to subtitle D of the federal Resource Conservation and Recovery Act of 1976, as amended.

(b) (I) The sufficiency of the financial assurance provided pursuant to the provisions of paragraph (a) of this subsection (3) for any proposed solid wastes disposal site and facility shall be reviewed as part of the department's review of the application for such proposed site and facility pursuant to the provisions of this section.

(II) The sufficiency of the financial assurance provided pursuant to the provisions of paragraph (a) of this subsection (3) for any solid wastes disposal site and facility that is in existence at the time the applicable regulations of the department become effective shall be reviewed pursuant to the procedures established by the department. Such review may be performed either by the department or by a private contractor hired by the department for the purpose of completing such review. The department is authorized to impose a fee for any such review that is performed by the department; except that such fee shall not exceed the actual documented costs incurred by the department in the performance of such review. Except as otherwise provided in this section, any such review that is performed by a private contractor shall be conducted pursuant to the provisions of section 30-20-103.7.

(3.5) The department, pursuant to the provisions of part 14 of article 30 of title 24, C.R.S., is authorized to contract with one or more private contractors for the purpose of conducting the third-party closure, postclosure care, or corrective action at a solid waste facility as may be necessary. The department is authorized to expend such moneys for closure, postclosure care, or corrective action as is made available to the department by operation of law from the financial assurance mechanisms provided by the owner or operator of the solid wastes site and facility. Any such contract shall be between the department and the private contractor. The owner or operator shall not be a party to such contract. The department may disallow a contractor because of conflicts of interest or other reasons. The department may contract with the governing body that issued the certificate of designation to conduct such closure, postclosure care, or corrective action.

(4) The rules promulgated by the solid and hazardous waste commission pursuant to this section shall comply with the federal regulations promulgated pursuant to subtitle D of the federal Resource Conservation and Recovery Act of 1976, as amended. Such rules shall require that all solid wastes disposal sites and facilities be fully in compliance with such rules by the date established in the federal Resource Conservation and Recovery Act of 1976, as amended, and its regulations.

Source: L. 92: Entire section added, p. 1276, � 3, effective July 1. L. 94: (4) amended, p. 33, � 3, effective March 9. L. 98: (3.5) added, p. 882, � 8, effective July 1. L. 2006: IP(1), (1)(e), (3)(a), and (4) amended, p. 1135, � 17, effective July 1.