76 sections in this chapter.
40E-63-.415 EVERGLADES PROGRAM
3.6K chars
(1) No Notice General Permits for Use of Works of the District within the C-139 Basin are hereby granted to the landowners of parcels of land that connect to or make use of the Works of the District within the C-139 Basin, subject to the requirements of this part of Chapter 40E-6…
40E-63-.420 EVERGLADES PROGRAM
1.4K chars
(1) For entities required to obtain a General Permit, a BMP Plan shall be submitted to the District within 30 days after the effective date of this part of Chapter 40E-63, F.A.C. Failure to provide a complete BMP Plan within 30 days from the effective date of this part of Chapter…
40E-63-.430 EVERGLADES PROGRAM
4.5K chars
(1) A General Permit is required for parcels of land that connect to or make use of the Works of the District within the C-139 Basin that have not been issued a waiver pursuant to Rule 40E-63.410, F.A.C., or do not qualify for a No Notice General Permit pursuant to Rule 40E-63.41…
40E-63-.432 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.113, 373.4592 FS. Law Implemented 373.016, 373.085, 373.086, 373.451, 373.453, 373.4592(4)(f) FS. History-New 1-24-02, Amended 6-20-07, Repealed 11-9-10.
40E-63-.434 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.113, 373.4592 FS. Law Implemented 373.016, 373.085, 373.086, 373.451, 373.453, 373.4592(4)(f) FS. History-New 1-24-02, Amended 6-20-07, Repealed 11-9-10.
40E-63-.435 EVERGLADES PROGRAM
4.2K chars
In order to obtain a General Permit, applicants shall submit a BMP Plan that includes a multi-level approach to implementation and operation for each crop or land use within each permit basin. A BMP Plan shall take into account site-specific conditions, potential phosphorus sourc…
40E-63-.436 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.083, 373.085, 373.086, 373.113, 373.4592 FS. Law Implemented 373.085, 373.4592 FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.437 EVERGLADES PROGRAM
6.3K chars
Applicants who propose to satisfy the water quality requirements of this part of Chapter 40E-63, F.A.C., by employing a BMP Plan other than those described in subsections 40E-63.435(1) and (2), F.A.C., may seek approval for an equivalent alternative through the District permit pr…
40E-63-.438 EVERGLADES PROGRAM
3.1K chars
An applicant may request approval for early implementation by opting to submit a proposal for voluntary implementation of additional BMPs (early BMPs), or a voluntary demonstration project that includes a BMP performance verification plan. Applicants electing these approaches mus…
40E-63-.439 EVERGLADES PROGRAM
4.0K chars
(1) Applicants for permit modifications, transfers and renewals must use the appropriate sections of Form 1045 (incorporated by reference in subsection 40E-63.430(2), F.A.C.), or equivalent electronic permitting application (e-permitting) tool. (2) Modifications and Letter Modifi…
40E-63-.440 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.113, 373.4592 FS. Law Implemented 373.016, 373.085, 373.086, 373.451, 373.453, 373.4592(4)(f) FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.441 EVERGLADES PROGRAM
1.9K chars
Pursuant to the EFA, Section 373.4592(4)(f)2., F.S., permit renewals issued pursuant to this part of Chapter 40E-63, F.A.C., are valid for a 5-year term, beginning 90 days after the effective date of this rule amendment. Subsequent permit renewals are effective for 5-year renewal…
40E-63-.442 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.4592 FS. Law Implemented 373.016, 373.085, 373.086, 373.423, 373.451, 373.453, 373.4592(4)(f) FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.443 EVERGLADES PROGRAM
0.9K chars
(1) The following permit application processing fees shall be paid to the District at the time the permit applications are filed. Permit Type New Renewal Modification Letter Modification Transfer General Permit $250 $250 $100 $0 $100 (2) Without the proper fee, the application sh…
40E-63-.444 EVERGLADES PROGRAM
7.1K chars
(1) All of the following standard limiting conditions paragraphs (a) through (u) shall be attached to all General Permits: (a) The permittee shall implement all elements and requirements of the approved BMP Plan according to schedule, including documentation of implementation, op…
40E-63-.446 EVERGLADES PROGRAM
4.8K chars
(1) If the C-139 Basin is determined to not meet the performance measures developed in accordance with Appendix B2 "C-139 Basin Performance Measure Methodology", dated November 2010, Appendix B2.1 "FORTRAN Program for Calculating C-139 Basin Flows and Phosphorus Loads" dated Janu…
40E-63-.450 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.083, 373.085, 373.086, 373.113, 373.4592 FS. Law Implemented 373.085, 373.4592 FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.452 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.083, 373.085, 373.086, 373.113, 373.4592 FS. Law Implemented 373.085, 373.4592 FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.454 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.083, 373.085, 373.086, 373.113, 373.4592 FS. Law Implemented 373.085, 373.4592 FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.456 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.083, 373.085, 373.086, 373.113, 373.4592 FS. Law Implemented 373.085, 373.4592 FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.458 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.083, 373.085, 373.086, 373.113, 373.4592 FS. Law Implemented 373.085, 373.4592 FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.460 EVERGLADES PROGRAM
0.2K chars
Rulemaking Authority 373.044, 373.083, 373.085, 373.086, 373.113, 373.4592 FS. Law Implemented 373.085, 373.4592 FS. History-New 1-24-02, Repealed 11-9-10.
40E-63-.461 EVERGLADES PROGRAM
10.9K chars
The District is authorized to seek any enforcement or corrective action available under Florida law for permittees out of compliance with the provisions of this chapter, pursuant to Chapter 373, F.S., and rules adopted thereunder. (1) If an individual permittee is determined to b…
40E-63-.462 EVERGLADES PROGRAM
3.2K chars
(1) In addition to implementing an approved BMP Plan, permittees may elect or be required to participate in a discharge monitoring program pursuant to Rules 40E-63.437, 40E-63.438, paragraph 40E-63.444(1)(r), subsection 40E-63.461(4) or 40E-63.461(6), F.A.C., and be subject to: (…
40E-63-.464 EVERGLADES PROGRAM
4.3K chars
For those applicants proposing to implement the Permit Basin Discharge Monitoring Program, the District-approved monitoring plan will be incorporated into a modified General Permit and the following limiting conditions shall be met in addition to the conditions indicated in Rule …
40E-63-.470 EVERGLADES PROGRAM
0.1K chars
Rulemaking Authority 373.044, 373.083, 373.085, 373.113, 373.4592 FS. Law Implemented 373.085, 373.4592 FS. History-New 1-24-02, Repealed 11-9-10.