R.110-20-1-.07 Review of Applications
2.6K chars
All applications received from eligible applicants will be reviewed to determine whether a project meets the REAP criteria and complies with these Rules. In making such a determination, the following factors will be considered: (1) Each application will be reviewed based upon an …
R.110-20-1-.08 Developers Reporting Requirements
2.5K chars
(1) After receipt of a Certificate of Compliance, applicants must submit annual progress reports to the Department for five years or until the minimum REAP program criteria (as set forth in O.C.G.A. Section 50-8-191(c)(3)) have been met, whichever is longer. A processing and moni…
R.110-20-1-.09 Amendment of Certification
1.7K chars
(1) If, at any time after a developer has received a Certificate of Compliance, the developer adds a facility(s) to a project (either inside or outside the boundaries of the original REAP project as defined by the map included in the initial REAP application pursuant to Section o…