Prompt payment

HRS §103-10.5 — under Chapter 103.

HRS §103-10.5

§103-10.5 Prompt payment. (a) Any money paid to a contractor shall be disbursed to subcontractors within ten days after receipt of the money in accordance with the terms of the subcontract; provided that the subcontractor has met all the terms and conditions of the subcontract and there are no bona fide disputes on which the procurement officer has withheld payment.

(b) Upon final payment to the contractor, full payment to the subcontractor, including retainage, shall be made within ten days after receipt of the money; provided there are no bona fide disputes over the subcontractor's performance under the subcontract.

(c) Where a subcontractor has provided evidence to the contractor of satisfactorily completing all work under their subcontract and has provided a properly documented final payment request as described in subsection (d) of this section, and:

all sums retained or withheld from a subcontractor and otherwise due to the subcontractor for satisfactory performance under the subcontract shall be paid by the procurement officer to the contractor and subsequently, upon receipt from the procurement officer, by the contractor to the subcontractor within the applicable time periods specified in subsection (b) and section 103-10. If the procurement officer or the contractor fails to pay in accordance with this section, a penalty of one and one-half per cent per month shall be imposed upon the outstanding amounts due that were not timely paid by the responsible party. The penalty may be withheld from future payment due to the contractor, if the contractor was the responsible party. If a contractor has violated subsection (b) three or more times within two years of the first violation, the contractor shall be referred by the procurement officer to the contractor license board for action under section 444-17(14).

(d) A properly documented final payment request from a subcontractor, as required by subsection (c), shall include:

The procurement officer shall return any final payment request that is defective to the contractor within seven days after receipt, with a statement identifying the defect.

(e) In the case of a construction contract, a payment request made by a contractor to the procurement officer that includes a request for sums that were withheld or retained from a subcontractor and are due to a subcontractor may not be approved under subsection (c) unless the payment request includes:

The procurement officer shall return any final payment request that is defective to the contractor within seven days after receipt, with a statement identifying the defect.

(f) This section shall not be construed to impair the right of a contractor or a subcontractor at any tier to negotiate and to include in their respective subcontracts provisions that provide for additional terms and conditions that are requested to be met before the subcontractor shall be entitled to receive final payment under subsection (c) of this section; provided that any such payments withheld shall be withheld by the procurement officer. [L 1983, c 277, §1; am L 2000, c 164, §2; am L 2006, c 291, §2]