electric vehicle building plan requirements — preemption

Idaho Code § 39-4109B — under IDAHO BUILDING CODE ACT.

Idaho Code § 39-4109B

39-4109B. electric vehicle building plan requirements — preemption. (1) Notwithstanding any other provision of law to the contrary, neither the state of Idaho nor any local government in Idaho shall adopt any requirement that an electric vehicle (EV) charging station, a designated EV parking space, an upgraded electrical conduit, or other infrastructure for the purpose of EV charging station installation be included in a building plan. (2) This section supersedes any local laws, ordinances, orders, rules, or regulations enacted by a political subdivision or municipality that requires an EV charging station, a designated EV parking space, an upgraded electrical conduit, or other infrastructure for the purpose of EV charging station installation to be included in a building plan.