Arbitration

30 ILCS 557/15, under Public Construction Contract Act.

30 ILCS 557/15

(30 ILCS 557/15)

    Sec. 15. Arbitration. A contractor and governmental entity may, by mutual agreement, arbitrate the contractor's entitlement to recover the actual increase in contract time or costs incurred because of a physical condition at the site. The judgment rendered may be entered in any court having jurisdiction over the matter.

(Source: P.A. 91-647, eff. 11-30-99.)