Transferring, assigning, or selling permit rights

Ind. Code § 14-34-5-2, under Chapter 5. Permit Terms.

Ind. Code § 14-34-5-2

Sec. 2. (a) A permittee may not transfer, assign, or sell the rights granted under a permit without the written approval of the director. (b) A successor in interest to a permittee who: (1) applies for a new permit within thirty (30) days of succeeding to the interest; and (2) obtains the bond coverage of the original permittee; may continue the surface coal mining and reclamation operations according to the approved mining and reclamation plan of the original permittee until the successor's application is granted or denied. [Pre-1995 Recodification Citation: 13-4.1-5-2.] As added by P.L.1-1995, SEC.27.