Sec. 4. A CMc contract may describe whether the CMc and the public agency agree to any cost overrun or delay damages or early completion incentives. As added by P.L.128-2014, SEC.1.
Ind. Code § 5-32-4-4, under CMc Contract.
Ind. Code § 5-32-4-4
Sec. 4. A CMc contract may describe whether the CMc and the public agency agree to any cost overrun or delay damages or early completion incentives. As added by P.L.128-2014, SEC.1.