Ind. Code § 32-30-16-1 Applicability; installation of communications infrastructure within existing electric easements; exemptions; property owner's exclusive remedy
2.6K chars
Sec. 1. (a) This chapter applies only to an electricity supplier (as defined in section 6 of this chapter). (b) This chapter applies to an action by a property owner against an electricity supplier that: (1) installs; (2) permits the installation of; or (3) intends to install; co…
Ind. Code § 32-30-16-10 Property owner's cause of action for decrease in value of real property; time limit for bringing action
0.7K chars
Sec. 10. Subject to sections 8(e) and 13 of this chapter, and except as provided by section 9 of this chapter, a property owner may bring a cause of action under section 12 of this chapter against an electricity supplier for damages relating to a decrease in value of the property…
Ind. Code § 32-30-16-11 Proof of damages; property owner's appraisal; electricity supplier's appraisal in case of dispute; property owner's acceptance; payment by electricity supplier
3.1K chars
Sec. 11. (a) In order to prove damages relating to a decrease in value of the property owner's real property caused by the attachment or installation of communications infrastructure within the electric easement, a property owner shall, at the property owner's expense and without…
Ind. Code § 32-30-16-12 Property owner's rejection of appraisal; property owner's right to file action; damages
1.0K chars
Sec. 12. (a) Subject to section 13 of this chapter, if: (1) the electricity supplier receives written notice from a property owner timely rejecting the electricity supplier's appraisal; and (2) the electricity supplier and property owner are unable to reach an agreement concernin…